BLD-Final | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
DOC - Permit Finaled | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/4/2020 | 5/5/2020 | 5/6/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Final | 5/1/2020 | 5/4/2020 | 5/5/2020 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Final | 4/30/2020 | 5/1/2020 | 5/1/2020 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// pend mech,, all else ok
|
BLD-Final | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// house ok now,, just needs final on the outside fireplace
|
BLD-Final | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// walk through only,, needs P/W hillside pass,, mech pass on outdoor fireplace,, verify underfloor seal etc., exterior reveal on foundation from landscape, fire caulk
|
BLD-Energy code compliance | 1/9/2020 | 1/9/2020 | 1/9/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Energy code compliance | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// met w/ owner, contractor and insulation contractor to go over minor issues,, will re-inspect in pm
|
BLD-Energy code compliance | 1/8/2020 | 1/8/2020 | 1/8/2020 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Energy code compliance | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson,, c/n posted,, needs to finish framing,, needs plumbing re-inspection on added fixtures, etc. re-insulate areas,, insulate rim as needed
|
BLD-Framing/Rough-in | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Other | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// soffits work in progress, ok
|
BLD-Wall Bracing | 10/30/2019 | 10/31/2019 | 10/31/2019 | A | PASS |
Tony Young
|
|
|
Dennis Phone #: ###-####,, exterior ok
|
BLD-Foundation | 8/21/2019 | 8/22/2019 | 8/22/2019 | A | PART |
Tony Young
|
|
|
1 oclock pour // mark Phone #: ###-####.. added to missed footings
|
BLD-Footing | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Tony Young
|
|
|
Mark-would like inspection as late AM as possible-has a pour time of 1:15 Phone #: ###-####
|
BLD-Footing | 8/19/2019 | 8/20/2019 | 8/21/2019 | A | PART |
Tony Young
|
|
|
Mark-would like inspection as late AM as possible-has a pour time of 1:15 Phone #: ###-####,, work was in progress,, needed soils approval,, now ok
|