BLD-Final | 2/27/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Jim Storey
|
|
|
Jim Phone #: ###-####
|
DOC - Permit Finaled | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | DONE |
Jim Storey
|
|
|
Jim Phone #: ###-#### 4.93
|
BLD-Final | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | FAIL |
Mike Jordan
|
|
|
Carl Phone #: ###-####. Complete fire cauliking in garage and provide blower door test results.
|
BLD-Framing/Rough-in | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Mike Jordan
|
|
|
sheet rock framing // Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Energy code compliance | 10/25/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Wall cover | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Framing/Rough-in | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Framing/Rough-in | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | FAIL |
Mike Jordan
|
|
|
Complete lateral bracing on A3 trusses. Complete fireblocking on furdowns. Nail off all simpson hangars and provide fixes for trusses at entry way. Ok to insulate.
|
BLD-Framing/Rough-in | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | CANC |
Mike Jordan
|
|
|
JIM Phone #: ###-####. moved to pm inspection.
|
BLD-Framing/Rough-in | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | FAIL |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Conference | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | DONE |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Wall Bracing | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Wall Bracing | 9/27/2019 | 9/27/2019 | 9/27/2019 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//sthds in wrong locations//framing and nailing needs address at portal frames//window added in shear location at front entry//2 hr wall does not reflect plans//
|
BLD-Wall Bracing | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Carl Phone #: ###-####. Needs to provide a full set of approved plans. Notes say there should be a total of eight pages of construction docs. Omly seven are provided. Wall bracing
|
BLD-Foundation | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Mike Jordan
|
|
|
stem wall // Willie Phone #: ###-####
|
BLD-Footing | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | PASS |
Mike Jordan
|
|
|
Sergio Phone #: ###-####
|
BLD-Footing | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | FAIL |
Mike Jordan
|
|
|
Sergio Phone #: ###-####. Approved plans shows duplex 1hr. wall seoeration, per scope of work, townhouses are being constructed, which require a 2hr. seperation. Plans to be resubmitted.
|
BLD-Footing | 8/8/2019 | 8/8/2019 | 8/8/2019 | P | FAIL |
Mike Jordan
|
|
|
surgeo Phone #: ###-####. No city approved plans on site.
|