BLD-Final | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PART |
Mike Jordan
|
|
|
Ed *screened Phone #: ###-####. OK for temp occ. once mech. passes final.
|
FIRE-Final Inspection | 8/4/2020 | 8/6/2020 | 8/6/2020 | A | PART |
Troy Cobbley
|
|
|
A temp for life safety until the project related fire alarm permit has been finaled.
Ed- */Screened*/ Phone #: ###-#### 7am inspection
|
FIRE-Final Inspection | 7/29/2020 | 7/30/2020 | 7/30/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled, need signs for fire dept access at the two entrances, need signage on electrical room door, need to test the door mags on main entrance.
Screened- ED Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Mike Jordan
|
|
|
screened // Ed Phone #: ###-####. 1st. floor ok.
|
BLD-Ceiling Grid Inspection | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. 2nd. floor grid and east stairwell only.
|
BLD-Ceiling Grid Inspection | 5/15/2020 | 5/15/2020 | 5/15/2020 | P | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. HArdlid in pool room ok.
|
BLD-Energy code compliance | 5/15/2020 | 5/15/2020 | 5/15/2020 | P | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. 2nd floor above ceiling ok.
|
BLD-Energy code compliance | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | CANC |
Mike Jordan
|
|
|
Ed *screened* Phone #: ###-####
|
BLD-Energy code compliance | 5/6/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Mike Jordan
|
|
|
Ed *screened* Phone #: ###-####. Pool room, north half of first floor.
|
BLD-Energy code compliance | 5/1/2020 | 5/4/2020 | 5/4/2020 | P | CANC |
Mike Jordan
|
|
|
screened // Ed Phone #: ###-####
|
BLD-Energy code compliance | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Mike Jordan
|
|
|
screened // Ed Phone #: ###-####. 1st. floor south half.
|
BLD-Energy code compliance | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | PASS |
Mike Jordan
|
|
|
Ed *cleared* Phone #: ###-####. 2nd. floor North half.
|
BLD-Energy code compliance | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Mike Jordan
|
|
|
screened // Ed Phone #: ###-####. 2nd floor, south half. fire blocking, 1st and 2nd. floors.
|
BLD-Framing/Rough-in | 4/14/2020 | 4/14/2020 | 4/14/2020 | P | PASS |
Mike Jordan
|
|
|
Ed **Cleared** Phone #: ###-####. 1st and 2nd. floor.
|
BLD-Framing/Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PART |
Mike Jordan
|
|
|
screened // Ed Phone #: ###-####. Needs to complete airseal. ok to one side.2nd. floor.
|
BLD-Framing/Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. Ok to insulate roof deck and 2nd floor were discussed. All missing holdowns have been installed.
|
FIRE-Conference | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | DONE |
Troy Cobbley
|
|
|
Ed and I discussed the combustible concealed pockets.
Ed Phone #: ###-####
|
BLD-Other | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Mike Jordan
|
|
|
2 hour wall for elevator shaft inspection - Ed Phone #: ###-####. Per the architect, the 2hr. assembly on plans is in correct and has provided the correct assembly.
|
BLD-Wall Bracing | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. All nailing on interior and exterior walls ok. All floor to floor straps ok except at pool area and at east interior stairs.
|
BLD-Framing/Rough-in | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PART |
Mike Jordan
|
|
|
Ed Phone #: ###-####. @hr. shaft for elevator. Need to verify type of sheet rock being used. GA file notes 1/2" type C, contractor has used 5/8 type X.
|
BLD-Wall Bracing | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | PART |
Mike Jordan
|
|
|
SHEAR // Ed Phone #: ###-####. Exterior and interior shear wall nailing. Needs to install all floor to floor straps, and fasten missed areas. Also received RFI ok an additional 7/16 OSB on high roof and noting 7/16 over pool area is ok due to 12" oc roof truss spacing.
|
BLD-Framing/Rough-in | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Mike Jordan
|
|
|
roof nailing // Ed Phone #: ###-####. Main roof structure.
|
BLD-Wall Bracing | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | PART |
Mike Jordan
|
|
|
Ed Phone #: ###-####. East exterior wall, 1st floor. Portion were meter pack is to be set only ok.
|
BLD-Foundation | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Mike Jordan
|
|
|
Ben Phone #: ###-####. remainder of interior thickend footings ok.
|
BLD-Foundation | 12/24/2019 | 12/26/2019 | 12/26/2019 | P | PART |
Dave Hannah
|
|
|
Ben Phone #: ###-#### int ftgs ok to pour
|
BLD-Foundation | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | FAIL |
Mike Jordan
|
|
|
Ben Phone #: ###-####
|
BLD-Foundation | 12/20/2019 | 12/23/2019 | 12/23/2019 | A | NR |
Mike Jordan
|
|
|
inspection not in plan mod location // Ben Phone #: ###-####
|
BLD-Foundation | 12/15/2019 | 12/16/2019 | 12/16/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Elevator pit walls and walls around swimming pool ok.
|
BLD-Foundation | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Brandon Shaw
|
|
|
Perimeter foundation...
|
BLD-Footing | 12/1/2019 | 12/2/2019 | 12/2/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru. Elevator pit, step footings and footings at pool ok.
|
BLD-Footing | 11/26/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron . Perimeter footings only, excluding step down areas by pool, pool footings and elevator pit.
|
BLD-Footing | 11/25/2019 | 11/26/2019 | 11/26/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 11/24/2019 | 11/25/2019 | 11/25/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru. Cancelled by contractor via phone call.
|
BLD-Footing | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Friday, November 22, 2019.
|