BLD-Final | 1/24/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Tell Riley
|
|
|
I''m available anytime after 11:00. Phone #: ###-#### Inspection requested via web by Gary Betts//trades finals complete//structure complete per plans and engineering--revised engineering for lateral bolts reviewed onsite from engineer//
|
DOC - Permit Finaled | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Framing/Rough-in | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | PART |
Tell Riley
|
|
|
Bob Phone #: ###-####//footing depth verified//electrical permit issued//framing member per engineering--knee braces need 3.5" at through bolts--verify with engineer or change to meet drawings//
|
BLD-Framing/Rough-in | 11/5/2019 | 11/6/2019 | 11/6/2019 | A | FAIL |
Tell Riley
|
|
|
Call 30 minutes ahead // Bob Phone #: ###-####//need verification of footings//owner will have hole drilled next to post to verify footings are under the posts//will need electrical inspection for conduit and electrical ran to pergola//re-inspection required//
|