BLD-Final | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Call // Eric Phone #: ###-####
|
DOC - Permit Finaled | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 12/19/2019 | 12/19/2019 | 12/19/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire aalrm inspection is complete, fire extinguisher has a current inspection tag and will be placed in discussed location. Final life fire safety inspection for area of work complete, signatures provided on permit sign off card for associated trades.
|
BLD-Ceiling Grid Inspection | 12/4/2019 | 12/4/2019 | 12/4/2019 | A | FAIL |
Brandon Shaw
|
|
|
All light fixtures (6), in new offices, to be secured to pan decking above ceiling grid... Need Ele cover approval...
|
BLD-Framing/Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | CANC |
Brandon Shaw
|
|
|
|
BLD-Wall cover | 12/2/2019 | 12/3/2019 | 12/3/2019 | P | DONE |
Brandon Shaw
|
|
|
Erick- if possible please call Phone #: ###-####
|
BLD-Wall cover | 11/6/2019 | 11/7/2019 | 11/7/2019 | P | PART |
Brandon Shaw
|
|
|
Ok to cover, pending Ele rough-in cover approval...
|
FIRE-Conference | 11/6/2019 | 11/6/2019 | 11/6/2019 | P | DONE |
Jim Page
|
|
|
Fire conference complete.
call to meet there // eric Phone #: ###-####
|