Information based on query as of Sunday, June 23, 2024.
Permit Information
Permit NumberBLD19-03041
StatusFinaled
Name EKC INC
Site Address 827 E PARK BLVD Unit: STE 100
Project NameTownsquare Media
Customer Number 
ePlanReviewYes
Description
**(TOWNSQUARE MEDIA – SUITE #100)** Permit is to remodel an existing 9,864 sq. ft. tenant space. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing walls, installation of nonbearing walls to create an (4) "Call Rooms" and (2) Offices, relocate an Entry door off the Lobby Area, remove wall between existing Conference Room and Office to enlarge Conference Room (364 sq ft), remove existing office stations, relocating of existing electrical work, plumbing work, mechanical work and installing interior finishes in compliance with Ch. 8 of the 2015 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **BJM**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/9/20201/10/20201/10/2020APASS
DetailsDave Hannah
late morning // Dale Phone #: ###-####
FIRE-Final Inspection1/9/20201/10/20201/10/2020ADONE
DetailsJim Page
Fire life safety inspection has been completed.

Dale Phone #: ###-####
FIRE-Final Inspection1/9/20201/9/20201/9/2020APASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete, signatures provided on permit sign off card.
FIRE-Final Inspection11/27/201911/29/201911/29/2019ACANC
DetailsTroy Cobbley
Need the fire alarm modifications addressed with a permit/inspection prior to a life safety inspection.

Dale Phone #: ###-####
BLD-Ceiling Grid Inspection11/26/201911/26/201911/27/2019PPASS
DetailsDave Hannah
Daniel Phone #: ###-####
FIRE-Conference11/26/201911/26/201911/26/2019ADONE
DetailsJim Page
I was requested for a fire sprinkler rough in inspection for area of work, noted that part of the areas in the scope of work, as of this entry, have been used before fire sprinkler inspections have been finaled, it appears that a fire alarm vendor has not been contacted for a site survey to verify if fire alarm modifications are required (Per the approved drawings it appears that fire alarm modifications will be required for the scope of work and there is no FIR permit in the system associated with this scope of work for fire alarm modifications) and no life fire safety inspection has been requested or performed. Remodeled areas are not to be used until the inspection process for areas of work has been completed. As mentioned, at the time of this entry no final inspections have been requested nor completed.
BLD-Ceiling Grid Inspection10/14/201910/15/201910/15/2019APART
DetailsDave Hannah
Dale Phone #: ###-#### needs to build new grid to old std lights ok
BLD-Final10/7/201910/7/201910/7/2019PPART
DetailsDave Hannah
Dale-Partial-Dave H can you pleae note what you do your inspecitons on-customer keeps saying phases but the permit doesn't reflect phases-Phone #: ###-#### phase 1 or area 1 ok to occ.
BLD-Framing/Rough-in9/12/20199/13/20199/13/2019APASS
DetailsDave Hannah
Josh Phone #: ###-####