BLD-Framing/Rough-in | 8/7/2020 | 8/10/2020 | 8/10/2020 | A | PART |
Tony Young
|
|
|
Dan *screened Phone #: ###-####// needs a mechanical permit and inspection// ok to insulate
|
BLD-Aging Inspection | 7/16/2020 | 7/16/2020 | 7/21/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 7/15/2020 | 7/15/2020 | 7/21/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PEND |
Dave Hannah
|
|
|
call ahead for access - screened // John Phone #: ###-#### framing ok c/n items completed all but for mec stiil needs mec rough in ok to insulate
|
BLD-Framing/Rough-in | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | NR |
Tony Young
|
|
|
call for access // Dan Phone #: ###-####// c/n posted needs plans, mech permit, seal pack, etc. .. ok to start stacking wall if needed
|
BLD-Foundation | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PART |
Tony Young
|
|
|
Jon Phone #: ###-####// interior slab footings work in progress,,ok
|
BLD-Foundation | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Tony Young
|
|
|
steam wall // Dan Phone #: ###-####
|
BLD-Footing | 10/4/2019 | 10/7/2019 | 10/7/2019 | A | PASS |
Tony Young
|
|
|
Dan Phone #: ###-####
|