BLD-Final | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Mike Jordan
|
|
|
recieved and reviewed special inspection report. Ok for final.
|
BLD-Conference | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | DONE |
Mike Jordan
|
|
|
Status? Project is completed. Will call contractor to schedule final and send special inspection report.
|
BLD-Wall Bracing | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Mike Jordan
|
|
|
shear // glenn Phone #: ###-####
|
BLD-Framing/Rough-in | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Mike Jordan
|
|
|
shear // glenn Phone #: ###-####
|
BLD-Footing | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Mike Jordan
|
|
|
glen Phone #: ###-####
|
BLD-Footing | 9/26/2019 | 9/27/2019 | 9/27/2019 | P | FAIL |
Brandon Shaw
|
|
|
As per plans- detail2, pg A1.2, no rebar on site....
|
BLD-Footing | 9/24/2019 | 9/25/2019 | 9/25/2019 | P | NR |
Mike Jordan
|
|
|
Geln Phone #: ###-####
|
BLD-Footing | 9/23/2019 | 9/24/2019 | 9/24/2019 | P | CANC |
Mike Jordan
|
|
|
Glen Phone #: ###-####
|