BLD-Final | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PASS |
Tell Riley
|
|
|
Tell,
It looks like all is finaled finally. Thanks,
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns//fire final ha been completed//final is complete//
|
DOC - Permit Finaled | | | 2/4/2020 | | DONE |
|
|
|
finaled, per Tell Riley
|
FIRE-Final Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
FIRE-Final Inspection | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | CANC |
Troy Cobbley
|
|
|
The project related fire alarm permit is not ready. This permit will need to be rescheduled. Troy,
Hopefully the alarm is correct this time. The code to get in the building is 1566
Thanks,
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
FIRE-Final Inspection | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | FAIL |
Troy Cobbley
|
|
|
Fire life safety wil be ok to sign off when the project related fire alarm permit is finaled.
Troy,
Here is my final fire.
Thanks,
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Final | 1/14/2020 | 1/15/2020 | 1/15/2020 | A | NR |
Tell Riley
|
|
|
verify tenant has vacated // Gemma Phone #: ###-####//discussed getting final on fire alarm with Todd, inspection scheduled, and he will get finals scheduled as well//Also let Jason know//
|
FIRE-Final Inspection | 12/5/2019 | 12/5/2019 | 12/6/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety is under a temp per agreement between the contractor and City of Boise. Needs fire alarm modifications prior to a final life safety sign off.
|
BLD-Final | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PART |
Tell Riley
|
|
|
Tell,
I am working on getting a temporary final for this project. I have the ok from jason Blais at the city. He just wants you to do a temp final to make sure all the rest is good. Call me when you can. Thanks, Todd Phone #: ###-#### Inspection requested via web by Todd Kurns//temp occupancy ok until fire permit is finaled//
|
FIRE-Final Inspection | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | NR |
Troy Cobbley
|
|
|
Not ready for final. Todd and I went over life safety requirements and it appears that a permit will be required for the fire alarm modifications needed due to the wall changes. Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Framing/Rough-in | 10/23/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Tell Riley
|
|
|
Tell,
Give me a call before you head to job. There is a card reader needed to access. Thanks Todd Phone #: ###-#### Inspection requested via web by Todd Kurns//ok to cover walls only//call for grid when ready//
|