BLD-Energy code compliance | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PASS |
Tell Riley
|
|
|
ok to cover, corrections made//walked framing with engineer, contractor, and I, corrections were made//
|
BLD-Energy code compliance | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | FAIL |
Tell Riley
|
|
|
cn issued to remove gyp to see framing corrections and insulation//
|
BLD-Energy code compliance | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//need to see length of lags used in ledger areas, boxes onsite are 6" and some areas would require a 10" lag for the 3" minimum needed per plans//will check other corrections when re-schedule//
|
BLD-Framing/Rough-in | 3/29/2020 | 3/30/2020 | 3/30/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//see corrections prior to any cover approval//need letter from engineer//ok to insulate//
|
BLD-Framing/Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//used as conference with engineer of record and contractor//some engineering will need to be completed and corrections made in framing//need I joist manual for plumbing in Is//need truss engineering//
|
BLD-Framing/Rough-in | 3/25/2020 | 3/26/2020 | 3/26/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Wall Bracing | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//nailing ok on firewall shear, per engineers email//
|
BLD-Wall Bracing | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | NR |
Tell Riley
|
|
|
carl - firewall nailing pattern Phone #: ###-####
|
BLD-Wall cover | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Mike Jordan
|
|
|
Firewall insulation Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Wall cover | 2/23/2020 | 2/24/2020 | 2/24/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funkrated separation walls only//blocking added at floor//insualtion needs to be R20 at exterior 2x8 rated walls//some insulation has fallen, would like to see as drywall is installed//
|
BLD-Wall cover | 2/20/2020 | 2/20/2020 | 2/20/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//still working on ELE// need to fix insulation//address fireblocking issue with Architect//remove siding in center unit to install 2 layers of 5/8 per detail//
|
BLD-Wall cover | 2/5/2020 | 2/5/2020 | 2/5/2020 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//CN posted//does not meet requirements for 2 hr assembly per plans//
|
BLD-Wall cover | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: ###-#### fire wall Inspection requested via web by Carl Funk
|
BLD-Wall cover | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk// needs plans
|
BLD-Wall Bracing | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk// exterior ok
|
BLD-Wall Bracing | 1/29/2020 | 1/29/2020 | 1/29/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//still need to fix hold down nailing//
|
BLD-Wall Bracing | 1/7/2020 | 1/8/2020 | 1/8/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//CN issued//not quite ready//
|
BLD-Wall Bracing | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PART |
Tell Riley
|
|
|
Inspection requested via web by Carl Funk//Nailing and hardware ok in most locations--some strapping needs lowered//location near fire separation wall will need tied into shear wall, waiting for engineered detail//
|
BLD-Wall Bracing | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Wall Bracing | 12/16/2019 | 12/16/2019 | 12/16/2019 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//used inspection as conference//
|
BLD-Footing | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | CANC |
Tell Riley
|
|
|
GILBERT Phone #: ###-####
|
BLD-Foundation | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PART |
Tell Riley
|
|
|
wip
|
BLD-Footing | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Tell Riley
|
|
|
SERGIO Phone #: ###-####//setbacks and rebar ok per plans//
|