BLD-Final | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PASS |
Dave Hannah
|
|
|
jeff Phone #: ###-####
|
FIRE-Final Inspection | 11/22/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete, signatures provided for associated trades on permit card.
|
BLD-Final | 11/4/2019 | 11/5/2019 | 11/5/2019 | A | PEND |
Dave Hannah
|
|
|
Jeff Phone #: ###-#### ok for tco
|
FIRE-Final Inspection | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | PART |
Jim Page
|
|
|
Temporary use of the area of work for life fire safety authorized for 45 days per conversation with Jason Blais. Fire sprinkler modifications have not been completed, new wall has not been placed, after wall is placed fire sprinkler modifications will need to be completed as discussed. Fire alarm modifications will be required in area of work as discussed. Final sign off for life fire safety is contingent upon fire sprinkler and fire alarm modifications being completed, inspected and passed.
Jeff Phone #: ###-####
|
FIRE-Final Inspection | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Jeff since a new wall and some sprinkler work is left to install. Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PART |
Dave Hannah
|
|
|
Ok for cover when electrical rough approved.
|
BLD-Final | 10/31/2019 | 10/31/2019 | | P | |
Dave Hannah
|
|
|
jeff Phone #: ###-####
|