Permit Information
Permit NumberBLD19-03504
StatusIssued
Name BOISE CITY BUILDING FACILITIES
Site Address 150 N CAPITOL BLVD
Project NameInnovative Performance Team TI
Customer Number 
ePlanReviewYes
Description
(INNOVATIVE PERFORMANCE TEAM - 1st FLOOR, CITY HALL) Permit is to remodel an existing Office Space (510 sq ft approx.) within the first floor of City Hall . Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing walls, removal of existing electrical work, relocating existing electrical and mechanical as needed (no new proposed); adding a new modular wall and door to ADA standards, relocate wall hung monitor, interior finishes in compliance with Ch. 8 of the 2015 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. No change in use or occupancy. Letter of Completion to be issued when Permit is finaled.**BJM**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/22/201911/22/201911/22/2019PPASS
DetailsDave Hannah
jeff Phone #: ###-####
FIRE-Final Inspection11/22/201911/22/201911/22/2019APASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete, signatures provided for associated trades on permit card.
BLD-Final11/4/201911/5/201911/5/2019APEND
DetailsDave Hannah
Jeff Phone #: ###-#### ok for tco
FIRE-Final Inspection11/4/201911/4/201911/4/2019PPART
DetailsJim Page
Temporary use of the area of work for life fire safety authorized for 45 days per conversation with Jason Blais. Fire sprinkler modifications have not been completed, new wall has not been placed, after wall is placed fire sprinkler modifications will need to be completed as discussed. Fire alarm modifications will be required in area of work as discussed. Final sign off for life fire safety is contingent upon fire sprinkler and fire alarm modifications being completed, inspected and passed.

Jeff Phone #: ###-####
FIRE-Final Inspection10/31/201911/1/201911/1/2019ACANC
DetailsTroy Cobbley
Cancel per Jeff since a new wall and some sprinkler work is left to install. Jeff Phone #: ###-####
BLD-Framing/Rough-in10/15/201910/15/201910/15/2019PPART
DetailsDave Hannah
Ok for cover when electrical rough approved.
BLD-Final10/31/201910/31/2019 P 
DetailsDave Hannah
jeff Phone #: ###-####