BLD-Blower Door Test Results | 5/7/2020 | 5/7/2020 | 5/7/2020 | A | DONE |
Tell Riley
|
|
|
5.3 ACH 50
|
BLD-Final | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Tell Riley
|
|
|
call for access Jeff Phone #: ###-####
|
DOC - Permit Finaled | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Energy code compliance | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####//corrections made//
|
BLD-Framing/Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####//most corrections made//still need to add nails to truss scabs per engineering//ok to insulate//
|
BLD-Framing/Rough-in | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | FAIL |
Tell Riley
|
|
|
Jeff Phone #: ###-####//CN posted//no plans onsite, a couple corrections noted//
|
BLD-Foundation | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | DEFR |
Tell Riley
|
|
|
no foundation inspection was requested//contractor assumes all liabilty for foundation//
|
BLD-Wall Bracing | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | PART |
Tell Riley
|
|
|
jeff Phone #: ###-####//shear ok when hot dipped galvanized nails have been added at PT plates//
|
BLD-Footing | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PART |
Tell Riley
|
|
|
James Phone #: ###-####//WIP//setbacks ok//will heat bar prior to pour//blankets onsite--cold weather techniques discusses//
|