BLD-Final | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Blower Door Test Results | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | DONE |
Mike Jordan
|
|
|
5.8
|
BLD-Final | 2/19/2020 | 2/20/2020 | 2/20/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Upper handrail exceeds the 38 inch max height requirement.
|
BLD-Energy code compliance | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Energy code compliance | 12/30/2019 | 1/2/2020 | 1/2/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs to install the vapor barrier.
|
BLD-Framing/Rough-in | 12/26/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Joel Hirtle
|
BLD-Wall Bracing | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Foundation | 11/20/2019 | 11/21/2019 | 11/21/2019 | P | PASS |
Mike Jordan
|
|
|
Dane- foundation wall Phone #: ###-####
|
BLD-Footing | 11/19/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|