Permit Information
Permit NumberBLD19-04518
StatusIssued
Name KREIZENBECK CONSTRUCTORS
Site Address 10255 W OVERLAND RD
Project NameSt Alphonsus Outpatient Clinic
Customer Number 
ePlanReviewYes
Description
(ST. ALPHONSUS OUTPATIENT MEDICAL CLINIC – 1ST STORY REMODEL) (DRH19-00518) The fire sprinkler system is used to substitute for a fire rated corridor. To remodel the 6,608 square foot 1st story of an existing outpatient medical clinic where no one is incapable of self-preservation. There is no remodel work proposed in the existing 1,208 square foot basement except for HVAC and plumbing work. Work is to include interior nonbearing walls, interior wall infills, gypsum board installed directly to the underside of roof trusses to create a compliant air barrier, four single-user toilet rooms accessible to the disabled, interior doors, exterior windows, suspended acoustical ceilings, gypsum board ceilings and soffits, millwork, and finishes. Structural work includes removing a load bearing wall and installing beams and columns in its place (concrete footing, tube steel columns with steel base plate and anchors to concrete, and steel beams). Special Inspection is required for soils, concrete, steel (including welding and bolting), and for anchors post-installed in hardened concrete. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/13/20208/13/20208/13/2020PPART
DetailsJim Page
Life fire safety inspection for phase 3A complete.

Requesting a fire life inspection in Phase 3A. please give me a call 30 minutes in advice if possible to allow tie for my electrician to be onsite for assistance. Please contact Markus Schlegel if you have questions. Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Ceiling Grid Inspection8/4/20208/4/20208/4/2020PPASS
DetailsMike Jordan
Requesting a ceiling grid inspection in the vestibule, lobby and room 106. Please contact Markus Schlegel if you have any questions. Thank you. Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Ceiling Grid Inspection7/30/20207/31/20207/31/2020APASS
DetailsMike Jordan
Requesting an inspection for Phase 3A. Please contact Markus Schlegel if you have questions. Thank you. Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Framing/Rough-in7/7/20207/7/20207/7/2020APASS
DetailsMike Jordan
Requesting an inspection on Exam room ; office door and wall infills. Restroom wall framing, lobby wall and soffit framing.
Thank you. Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Final6/15/20206/16/20206/16/2020PPART
DetailsTony Young
Requesting a partial building final after the fire life safety inspection phase 2 for requested for 7:30am. Please call me for confirmation. Phone #: ###-#### Inspection requested via web by Markus Schlegel// phase 2 ok
FIRE-Final Inspection6/15/20206/16/20206/16/2020APART
DetailsTroy Cobbley
Phase two life safety passed.
BLD-Ceiling Grid Inspection5/28/20205/28/20205/28/2020PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Framing/Rough-in5/8/20205/11/20205/11/2020APASS
DetailsMike Jordan
Phase II wall ; hard lid inspection framing inspection. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Interior steel stud framed walls and hardlids for phase 2 ok.
BLD-Final4/21/20204/22/20204/22/2020APART
DetailsMike Jordan
Requesting an inspection after the Fire Alarm ; Fire Life Safety inspection is complete tomorrow morning.
Thank you, Phone #: ###-#### Inspection requested via web by Markus Schlegel. Temp occ. ok for phase 1 only ok to occupy.
FIRE-Final Inspection4/21/20204/22/20204/22/2020APART
DetailsTroy Cobbley
Life safety for phase 1 passed. Fire sprinkler and fire alarm complete.

Requesting an inspection after the Fire Alarm inspection is complete tomorrow morning.
Thank you, Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Final4/20/20204/21/20204/21/2020ACANC
DetailsMike Jordan
Requesting a late morning Building Final for Temp CofO Phase 1
Fire Alarm Inspection is at 7am
Fire Life Safety is scheduled for after. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel Inspection cancelled from web by: Markus Schlegel
FIRE-Final Inspection4/20/20204/21/20204/21/2020ACANC
DetailsTroy Cobbley
Final Fire Life Safety Phase 1 after Fire Alarm Inspection at 7am Phone #: ###-#### >> Inspection requested via web by Markus Schlegel Inspection cancelled from web by: Markus Schlegel
BLD-Ceiling Grid Inspection4/1/20204/2/20204/2/2020PPASS
DetailsMike Jordan
Phase 1 only. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Phase 1 grid ok.
BLD-Ceiling Grid Inspection3/23/20203/24/20203/24/2020ACANC
DetailsMike Jordan
Requesting a late morning inspection on exam rooms and offices on the north ; east side of phase 1. Thank you Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Framing/Rough-in3/18/20203/18/20203/18/2020PPASS
DetailsMike Jordan
Interior wall and soffit framing in Hall H11 ; Room 105. Phone #: ###-#### Inspection requested via web by Markus Schlegel
BLD-Framing/Rough-in3/17/20203/19/20203/18/2020PCANC
DetailsMike Jordan
Interior soffit & wall framing in team center room 105 & Hall H11. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel Inspection cancelled from web by: Markus Schlegel
BLD-Framing/Rough-in3/9/20203/10/20203/10/2020APART
DetailsMike Jordan
Interior framing w/ structural steel elements and 3 exterior window framing additions. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Phase 1 interior steel stud framed walls and hardlid ok pending electrical and plumbing rough in inspections. Also structural steel columns and beams in phase 1 require special inspection. Noted bolt holes are over sized and will require plate washers.
BLD-Footing2/10/20202/11/20202/11/2020APASS
DetailsMike Jordan
Footing in crawl space. Can be viewed from floor above. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Interior column pad footing in crawl space ok.
BLD-Final8/13/20208/14/2020 A 
DetailsMike Jordan
Requesting a building final in Phase 3A. Please contact Markus Schlegel if you have questions. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel