BLD-Framing/Rough-in | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PASS |
Jim Storey
|
|
|
Wall/roof shear inspection for framing. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
BLD-Concrete | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Jim Storey
|
|
|
Slab inspection for Building A, pour scheduled for AM on 4/2/20 Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
BLD-Foundation | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Jim Storey
|
|
|
Foundation wall inspection. Looking to pour ~2:00pm if possible. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
BLD-Foundation | 3/11/2020 | 3/12/2020 | 3/12/2020 | P | PASS |
Jim Storey
|
|
|
Footing rebar inspection, looking to pour late 3/12 or early 3/13. Bar should be tied ~2pm Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|