BLD-Final | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Dave Hannah
|
|
|
Alex *screened* Phone #: ###-####
|
FIRE-Final Inspection | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Alex *screened* Phone #: ###-####
|
BLD-Final | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | NR |
Tell Riley
|
|
|
Alex Phone #: ###-####//let Alex know he need a mechanical final, fire sprinkler final and a fire lafe safety inspection prior to a building final//
|
BLD-Final | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | CANC |
Tell Riley
|
|
|
screened // Alex Phone #: ###-####
|
BLD-Energy code compliance | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Tell Riley
|
|
|
Alex Phone #: ###-####//blow in insulation added to batts in attic//walls were covered with VB//post insulation certificate for final inspection//
|
BLD-Energy code compliance | 5/8/2020 | 5/8/2020 | 5/8/2020 | P | FAIL |
Tell Riley
|
|
|
Alex - Gates close at 2pm Phone #: ###-####//door in kithchen needs to swing in direction on plans and have landing//need to install R49 insulaton in attic//add vapor barrier at exterior walls per plans//
|
BLD-Framing/Rough-in | 5/5/2020 | 5/5/2020 | 5/6/2020 | P | PART |
Tell Riley
|
|
|
framing corrections ok, need fire sprinkler approval prior to cover, ok to insulate WALLS only//
|
BLD-Framing/Rough-in | 5/4/2020 | 5/5/2020 | 5/5/2020 | A | NH |
Tell Riley
|
|
|
Alex Phone #: ###-####//no one onite doors locked, knocked on front door no one answered//sprinkler permit has not had a rough in inspection//
|
BLD-Conference | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | DONE |
Tell Riley
|
|
|
Conference with Alex - Requesting Bob A as well. Please call ahead Phone #: ###-####//conference complete, new CN posted for framing corrections//
|
FIRE-Conference | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | DONE |
Troy Cobbley
|
|
|
It appears sprinkler modifications are required. Contractor stated per the Architect sprinkler protection was not required. I let him know that a Demo permit would still be needed for the work. Conference with Alex - Check out existing sprinkler system Phone #: ###-####
|
BLD-Framing/Rough-in | 4/22/2020 | 4/23/2020 | 4/23/2020 | A | FAIL |
Tell Riley
|
|
|
Alex Phone #: ###-####//need mechanical, plumbinng and fire sprinkler permits//CN posted for framig corrections as well, see correction notice posted onsite and plans//
|