BLD-Framing/Rough-in | 8/5/2020 | 8/5/2020 | 8/5/2020 | A | PART |
Tell Riley
|
|
|
truss Phone #: ###-#### Inspection requested via web by Shane Shade////see shane for truss bracing corrections and hager nailing//
|
BLD-Wall Bracing | 7/10/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Tell Riley
|
|
|
exterior shear Phone #: ###-#### Inspection requested via web by Shane Shade//nailing ok//see plans for straps missing or need moved-circled in black pen//exterior nailing and straping only//
|
BLD-Concrete | 5/22/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade
|
BLD-Foundation | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//ok when rebar clearances are achieved//
|
BLD-Footing | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//setbacks set by surveyor//bar installed, ok when verts are under horz bar, add corner bar where discussed//
|
BLD-Conference | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | CANC |
Tell Riley
|
|
|
We need the initial grading inspection done for excavation to start. Phone #: ###-#### Inspection requested via web by Ed Kron
|
BLD-Framing/Rough-in | 8/13/2020 | 8/14/2020 | | A | |
Tell Riley
|
|
|
bearing Phone #: ###-#### >> Inspection requested via web by Shane Shade
|