BLD-Framing/Rough-in | 3/1/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Dave Hannah
|
|
|
Call Jimmy (Contractor) prior to arriving to job site. Ring on doorbell so owner lets you in the back. Phone #: ###-#### Inspection requested via web by Jimmy Medina
|
BLD-Wall Bracing | 3/1/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Dave Hannah
|
|
|
Call Jimmy (contractor prior to arriving to site. Ring on the doorbell so owner can let you in the back. Phone #: ###-#### Inspection requested via web by Jimmy Medina
|
BLD-Foundation | 2/21/2020 | 2/24/2020 | 2/24/2020 | A | PART |
Tell Riley
|
|
|
flatwork // Max Phone #: ###-####//heaters were installed overnight,, no frost was observed in footing areas//talked with contractor and he will be pre-heating prior to pour//frost protection will need to be maintained
|
BLD-Footing | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | FAIL |
Tell Riley
|
|
|
re-inspect pour around 12//ground is still frozen in a good portion of the footings//some of the flatwork sub grade is also frozen//
|
BLD-Footing | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | NR |
Tell Riley
|
|
|
Jimmy Phone #: ###-####//still working in digging//advised to heat for frost protection//will re-inspect 2/21//
|
BLD-Foundation | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | NR |
Dave Hannah
|
|
|
Jimmy Phone #: ###-####
|
BLD-Foundation | 2/18/2020 | 2/18/2020 | 2/18/2020 | P | FAIL |
Tell Riley
|
|
|
Jimmy Phone #: ###-####//setbacks ok per plans//still need 24 inch frost depth//ground is frozen in some locations//
|
BLD-Foundation | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | FAIL |
Tell Riley
|
|
|
Matt Phone #: ###-####//contact did not answer//left CN with owner//footings need to be 12" wide and 24" below grade for frost protection//find corner pin to measure setbacks//
|