BLD-Blower Door Test Results | 7/17/2020 | 7/17/2020 | 7/17/2020 | A | DONE |
Mike Jordan
|
|
|
4.4
|
BLD-Final | 7/16/2020 | 7/17/2020 | 7/17/2020 | A | PASS |
Mike Jordan
|
|
|
Garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover
|
DOC - Permit Finaled | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 3/20/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Tell Riley
|
|
|
corrections made//need to add sds screws to 2x4 bottom chord on girder truss//insulation ok as well//
|
BLD-Framing/Rough-in | 3/20/2020 | 3/20/2020 | 3/20/2020 | P | NR |
Tell Riley
|
|
|
Joist in garage Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Framing/Rough-in | 3/16/2020 | 3/17/2020 | 3/17/2020 | P | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//need Mechanical and stove inspections//correction notice posted for various framing issues//
|
BLD-Other | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | PASS |
Tell Riley
|
|
|
Soffit sheetrock Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Wall Bracing | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//nailing ok// still need to add blocks//were working on them when i left//
|
BLD-Wall Bracing | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//need to add hot dipped galvanized nails, and blocking see red marks on plans//
|
BLD-Foundation | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | PART |
Tell Riley
|
|
|
Mark- Pour time 11am STEM WALL Phone #: ###-####//WIP//discussed with contractor about cold weather protection//cold weather protection will need to be provided//
|
BLD-Footing | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PART |
Tell Riley
|
|
|
Pour at 1:30 // Mark Phone #: ###-####//setbacks ok per plans//WIP//
|