BLD-Ceiling Grid Inspection | 8/6/2020 | 8/7/2020 | 8/7/2020 | A | PASS |
Tell Riley
|
|
|
Miles *screened* Phone #: ###-####//mechanical passed//ok to fill grid in phase 2//
|
BLD-Ceiling Grid Inspection | 8/4/2020 | 8/5/2020 | 8/5/2020 | P | PART |
Tell Riley
|
|
|
Miles- */Screened*/ Phone #: ###-####//grids phase 2 ok pending mechanical rough in//do not cover until mechanical has passed//
|
BLD-Ceiling Grid Inspection | 7/22/2020 | 7/23/2020 | 7/23/2020 | A | PART |
Tell Riley
|
|
|
Request to lay ceiling tiles in areas with passed overhead inspections Phone #: ###-#### Inspection requested via web by Miles Gastil//ok to cover grid in phase one//
|
BLD-Ceiling Grid Inspection | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PART |
Tell Riley
|
|
|
screened // Miles Phone #: ###-####//phase one grid areas//mech passed//Fire sprinkler passed//ok to flood grid in areas of phase one that electrical has passed//other areas are pending eletrical approval//
|
BLD-Framing/Rough-in | 6/25/2020 | 6/26/2020 | 6/26/2020 | A | PART |
Tell Riley
|
|
|
screened // John Phone #: ###-####//areas marked on plans ok per plans and engineering clarification//some areas are pending ELE rough and were marked accordingly//
|
BLD-Framing/Rough-in | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PART |
Tell Riley
|
|
|
Confirmation to sheetrock inspected soffits throughout Phone #: ###-#### Inspection requested via web by Miles Gastil//ok to cover soffits, 2-where mechanical is present, and fire spinklers signed off, also areas where no mechanical, but electrical and fire sprinklers are approved//framing was looked at previously, ok now that rough ins have been approved//
|
BLD-Framing/Rough-in | 4/24/2020 | 4/24/2020 | 4/24/2020 | A | PEND |
Tell Riley
|
|
|
Soffit inspection Phone #: ###-#### Inspection requested via web by Miles Gastil//walk through on soffits, framing appears to be ok, need fire sprinkler approval, and mechanical pass//
|
BLD-Framing/Rough-in | 4/7/2020 | 4/7/2020 | 4/7/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Miles Gastil//marked on electrical plan areas marked in green ok//
|
BLD-Framing/Rough-in | 3/30/2020 | 3/31/2020 | 3/31/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Miles Gastil//areas marked in pink on electrical page and approved for cover by electrical ok for wall cover only//
|