BLD-Energy code compliance | 8/10/2020 | 8/10/2020 | 8/10/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//east wall 1st floor interior shear wall ok//anchor bolts installed//discussed safety glazing for windows and areas//ok to cover separation wall for shear//
|
BLD-Framing/Rough-in | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PART |
Tell Riley
|
|
|
Foam seal/ Framing Phone #: ###-#### Inspection requested via web by Shane Shade//still need anchor bolts installed//a couple other framing issues noted, see Russell for corrections//ok to insulate the rest of walls//
|
BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 | A | PART |
Tell Riley
|
|
|
Structural/Bearing points Phone #: ###-#### Inspection requested via web by Shane Shade//See Russell for notes on corrections for beams, posts, joists,bearing, anchor bolts, and hold downs//ok to insulate separation walls only at this time//this inspection was not a complete framing inspection//
|
BLD-Framing/Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | A | PART |
Tell Riley
|
|
|
Truss/consultation---Please call 30 minutes prior Phone #: ###-#### Inspection requested via web by Shane Shade//truss bracing ok//provide engineering for mechanical added to attic space//
|
BLD-Framing/Rough-in | 7/9/2020 | 7/9/2020 | 7/9/2020 | P | NR |
Tell Riley
|
|
|
Truss Phone #: ###-#### Inspection requested via web by Shane Shade//still need truss bracing installed//CN issued//
|
BLD-Framing/Rough-in | 7/2/2020 | 7/2/2020 | 7/2/2020 | A | NR |
Tell Riley
|
|
|
Truss Inspection Phone #: ###-#### Inspection requested via web by Shane Shade//trusses need bracing per the enginering//
|
BLD-Wall Bracing | 6/12/2020 | 6/12/2020 | 6/12/2020 | A | PART |
Tell Riley
|
|
|
Final shear Phone #: ###-#### Inspection requested via web by Shane Shade//add nails for 3" edge nailing--shane will verify complete prior to installing the remaing house wrap//nail straps where nails are missed//add straps on type 3 shear walls at headers and sill plates per details//other exterior shear nailing areas ok per the plans//
|
BLD-Wall Bracing | 6/8/2020 | 6/8/2020 | 6/8/2020 | A | PART |
Tell Riley
|
|
|
1st floor shear Phone #: ###-#### Inspection requested via web by Shane Shade//1st floor shear nailing re-inspection//nails were added in areas in accordance with shear schedule//
|
BLD-Wall Bracing | 6/4/2020 | 6/4/2020 | 6/4/2020 | A | PART |
Tell Riley
|
|
|
1st floor shear Phone #: ###-#### Inspection requested via web by Shane Shade//add nailing per shear schedule-in areas on wall marked in green-other areas on first floor appear to be ok//this inspection was for exterior nailing on the first floor only//will call in foe re-inspction//
|
BLD-Footing | 5/5/2020 | 5/5/2020 | 5/5/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Concrete | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//slab vb and insulation installed//
|
BLD-Foundation | 4/7/2020 | 4/7/2020 | 4/7/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade//WIP//
|
BLD-Footing | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Shane Shade
|