BLD-Final | 3/20/2020 | 3/26/2020 | 3/26/2020 | P | PASS |
Dave Hannah
|
|
|
On Site Contact: Mierins Rozentals. ###-#### Please call to coordinate arrival times, thank you!
Final Electrical is scheduled for 3/26 as well in the AM, please make sure that electrical inspector passes off first so that we don''t fail for that Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | DONE |
Tell Riley
|
|
|
Taylor Barton is the on site contact Phone #: ###-#### Inspection requested via web by BRS Permitting//onsite ok, needs electrical,, no changes to structure required per engineer//pend electrical pass//
|