BLD-Energy code compliance | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Jim Storey
|
|
|
Inspection of drywall for WUI at underside of exterior porch and soffit Phone #: ###-#### Inspection requested via web by Kristen McNeill
|
BLD-Framing/Rough-in | 7/14/2020 | 7/15/2020 | 7/15/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kristen McNeill// frame ok pending electrical rough pass
|
BLD-Framing/Rough-in | 7/14/2020 | 7/15/2020 | 7/14/2020 | P | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kristen McNeill Inspection cancelled from web by: Kristen McNeill
|
BLD-Wall Bracing | 7/7/2020 | 7/9/2020 | 7/9/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kristen McNeill,, roof connections ok
|
BLD-Footing | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | PASS |
Tony Young
|
|
|
reinspection footing Phone #: ###-#### Inspection requested via web by Kristen McNeill
|
BLD-Footing | 6/2/2020 | 6/3/2020 | 6/3/2020 | P | NR |
Tony Young
|
|
|
reinspection footing Phone #: ###-#### Inspection requested via web by Kristen McNeill
|
BLD-Footing | 6/1/2020 | 6/2/2020 | 6/2/2020 | P | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kristen McNeill//CN left in box with plans//need to clean footings--loose material in bottoms//rebar needs to be installed per the engineering details//re-inspection required//
|
BLD-Footing | 5/26/2020 | 5/27/2020 | 5/26/2020 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kristen McNeill Inspection cancelled from web by: Kristen McNeill
|