BLD-Energy code compliance | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 7/15/2020 | 7/16/2020 | 7/16/2020 | A | NR |
Mike Jordan
|
|
|
Inspection requested via web by Rob Johnson. Still needs to justify No bearing on A08 truss.
|
BLD-Energy code compliance | 7/13/2020 | 7/15/2020 | 7/15/2020 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Johnson
|
BLD-Framing/Rough-in | 7/15/2020 | 7/15/2020 | 7/15/2020 | A | FAIL |
Mike Jordan
|
|
|
Still needs to fireblock concealed area adjacent to archway and justify no continous bearing under A08 truss.
|
BLD-Framing/Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Johnson. NAil 2 ply truss per the engineering. A portion of the A08 truss shows continous bearing on the bottom chord, justify no bearing. Fireblock concealed area at ceiling level adjacent to archway. Ok to insulate.
|
BLD-Wall Bracing | 6/30/2020 | 6/30/2020 | 6/30/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD-Foundation | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Mike Jordan
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|