INSP - Final | 7/2/1996 | 7/2/1996 | 7/2/1996 | | PASS |
|
|
|
/ / 338 -
|
INSP - Final | 7/2/1996 | 7/2/1996 | 7/2/1996 | | PASS |
|
|
|
/ / 338 -
|
INSP - Final | 7/1/1996 | 7/2/1996 | 7/2/1996 | P | NR |
|
|
|
07/03/96 338 - ###-#### FOR ACCESS JAMES ROWAN FOR ACCESS PER YOU NOT RE
|
INSP - Letter of compliance | 7/2/1996 | 7/2/1996 | 7/2/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED 10849
|
INSP - Letter of compliance | 7/2/1996 | 7/2/1996 | 7/2/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED 10849
|
INSP - Final | 4/18/1996 | 4/18/1996 | 4/18/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED screw atchment not complet.
|
INSP - Framing/ Rough-in | 8/7/1995 | 8/7/1995 | 8/7/1995 | | PASS |
|
|
|
/ / 338 - correction removed
|
INSP - Framing/ Rough-in | 8/2/1995 | 8/3/1995 | 8/2/1995 | A | FAIL |
|
|
|
08/02/95 338 - 1 complete the air infill pac 2 tighten all trimmer to header acd cripple to header and sills 3 6' header requires double trimmers 4 class 1 duct
|
INSP - Footings | 7/10/1995 | 7/10/1995 | 7/10/1995 | | PASS |
Jim Storey
|
|
|
15 min
|