INSP - Final | 9/15/1995 | 9/15/1995 | 9/15/1995 | P | PASS |
Wes Worcester
|
|
|
09/15/95 342 -
|
INSP - Letter of compliance | 9/15/1995 | 9/15/1995 | 9/15/1995 | | PASS |
Wes Worcester
|
|
|
/ / 342 - c/c #10076
|
INSP - Energy code compliance | 8/16/1995 | 8/17/1995 | 8/17/1995 | A | PASS |
Wes Worcester
|
|
|
08/16/95 342 - did all but replace deformeed let ins. g.w.b. shear garag
|
INSP - Energy code compliance | 8/16/1995 | 8/17/1995 | 8/17/1995 | A | PASS |
Wes Worcester
|
|
|
08/16/95 342 - did all but replace deformeed let ins. g.w.b. shear garag
|
INSP - Framing/ Rough-in | 8/16/1995 | 8/16/1995 | 8/16/1995 | | NR |
Wes Worcester
|
|
|
/ / 342 - 09 explained c/n. 45 min.
|
INSP - Energy code compliance | 8/15/1995 | 8/15/1995 | 8/15/1995 | P | NR |
Wes Worcester
|
|
|
08/15/95 342 - requested conference with framer, will meet corey and fra 15 min
|
INSP - Energy code compliance | 8/15/1995 | 8/15/1995 | 8/15/1995 | P | NR |
Wes Worcester
|
|
|
08/15/95 342 - requested conference with framer, will meet corey and fra 15 min
|
INSP - Energy code compliance | 8/14/1995 | 8/14/1995 | 8/14/1995 | P | PASS |
Wes Worcester
|
|
|
08/14/95 342 - 44 ok c/n reissued. 30 min $30 reinspection fee due.
|
INSP - Energy code compliance | 8/14/1995 | 8/14/1995 | 8/14/1995 | P | PASS |
Wes Worcester
|
|
|
08/14/95 342 - 44 ok c/n reissued. 30 min $30 reinspection fee due.
|
INSP - Framing/ Rough-in | 8/14/1995 | 8/14/1995 | 8/14/1995 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - 09. c/n not done or removed. c/n reissued w/$30 reinspection
|
INSP - Framing/ Rough-in | 8/10/1995 | 8/10/1995 | 8/10/1995 | P | FAIL |
Wes Worcester
|
|
|
08/10/95 342 - 09. c/n. 30 min
|
INSP - Footings | 7/20/1995 | 7/20/1995 | 7/20/1995 | P | PASS |
Wes Worcester
|
|
|
07/20/95 342 - 05 0k. 06. ok. question on modification of plan and footi not modified it is ok. 30 min
|