Permit Information
Permit NumberBLD95-00393
StatusFinaled
Name P.E.R.S.I.
Site Address 820 W WASHINGTON ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Convert three floors (2stories over a basement) of an existing, fully sprinklered,B2 - office occupancy to a temporary E1 - educational occupancy for use by the Boise School District During the Boise High School renovation project. No structural work is involved in this interior remodel project. These plans were reviewed and approved by Ken Hartell of the State Department of Labor and Industrial Services. All work is to be done as per plans on file with the City of Boise. FINAL CERTIFICATE OF VALUE ON FILE ELE.37,000 PLG. 20,890 MECH. 12,297 FIRE SPRINKLER. 10,900
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final8/4/19988/4/19988/4/1998PPASS
DetailsCarl Dependahl
plbg ok
INSP - Final10/9/199510/9/199510/9/1995 FAIL
DetailsCarl Dependahl
/ / 340 -
INSP - Temporary occupancy10/9/199510/9/199510/9/1995 PASS
DetailsCarl Dependahl
/ / 340 -
INSP - Temporary occupancy10/9/199510/9/199510/9/1995 PASS
DetailsCarl Dependahl
/ / 340 -
INSP - Ceiling grid9/14/19959/15/19959/15/1995AFAIL
DetailsCarl Dependahl
09/14/95 340 -
INSP - Ceiling grid9/6/19959/6/19959/6/1995PFAIL
DetailsCarl Dependahl
09/06/95 340 -
INSP - Ceiling grid8/10/19958/11/19958/11/1995AFAIL
DetailsCarl Dependahl
08/10/95 340 -
INSP - Framing/ Rough-in8/11/19958/11/19958/11/1995 FAIL
DetailsCarl Dependahl
/ / 340 -
INSP - Framing/ Rough-in7/21/19957/21/19957/21/1995PNR
DetailsCarl Dependahl
REINSPECT. THIS IS "SHELL"...STEED CONST HAS "FINISH"... NEED ARCH'S DETAIL FOR 1 HR. AT CORRIDORS, EXITS, ETC. OK TO ROCK 1 SIDE.
INSP - Framing/ Rough-in7/19/19957/20/19957/20/1995AFAIL
DetailsCarl Dependahl
C/N ON FIRESTOPPING, 1HR WALLS, ETC...SEE C/N; PARTIAL ONLY, WHAT PORTION OF BLDG. READY FOR INSP?