INSP - Final | 5/1/1996 | 5/1/1996 | 5/1/1996 | | PASS |
Bob Archibald
|
|
|
ROUTED TO CATHY FOR ISSUANCE OF CO.
|
Permanent Occupancy | | 5/1/1996 | 5/1/1996 | | DONE |
|
|
|
|
INSP - Final | 4/3/1996 | 4/3/1996 | 4/3/1996 | P | TEMP |
|
|
|
|
INSP - Final | 3/27/1996 | 3/29/1996 | 3/29/1996 | P | CANC |
|
|
|
contractor called to cancel.
|
INSP - Energy code compliance | 2/20/1996 | 2/20/1996 | 2/20/1996 | | PASS |
|
|
|
|
INSP - Wall cover | 2/16/1996 | 2/20/1996 | 2/20/1996 | A | PASS |
|
|
|
1hr lid, 1st layer.
|
INSP - Framing/Rough-in | 2/15/1996 | 2/16/1996 | 2/16/1996 | A | FAIL |
|
|
|
BASEMENT / LID OK TO COVER.
|
INSP - Framing/Rough-in | 1/29/1996 | 1/30/1996 | 1/30/1996 | P | PART |
|
|
|
01/30/96 338 -
|
INSP - Conference | 1/10/1996 | 1/10/1996 | 1/10/1996 | | PASS |
|
|
|
/ / 338 - WANT TO KNOW IF THEY CAN LEAVE PART OF THE BUILDING UNFINISH
|
INSP - Framing/Rough-in | 1/10/1996 | 1/10/1996 | 1/10/1996 | | PART |
|
|
|
/ / 338 - OK TO DRYWALL ENOUGH TO START THE CORRIDOR I-HOUR TUNNEL
|
INSP - Framing/Rough-in | 1/10/1996 | 1/10/1996 | 1/10/1996 | P | CANC |
Wes Worcester
|
|
|
01/10/96 342 - partial?
|
INSP - Conference | 12/8/1995 | 12/8/1995 | 12/8/1995 | | |
|
|
|
/ / 338 -
|
INSP - Foundation | 11/20/1995 | 11/21/1995 | 11/21/1995 | P | PASS |
|
|
|
11/21/95 338 - LATE PM
|
INSP - Foundation | 11/16/1995 | 11/16/1995 | 11/16/1995 | P | PASS |
|
|
|
PARTIAL
|
INSP - Framing/Rough-in | 11/15/1995 | 11/16/1995 | 11/16/1995 | A | PART |
|
|
|
PARTIAL
|
INSP - Foundation | 11/13/1995 | 11/14/1995 | 11/14/1995 | A | PASS |
|
|
|
11/13/95 338 - LATE AM...... ì
|
INSP - Foundation | 11/9/1995 | 11/13/1995 | 11/9/1995 | A | PASS |
|
|
|
11/09/95 338 - basement walls only r-bar placed only. waterstop added is not installed correctly. joints are not welded only laped feon 6" to in some cases it is next to the formwork
|
INSP - Conference | 11/9/1995 | 11/9/1995 | 11/9/1995 | | PASS |
|
|
|
/ / 338 - here are you?
|
INSP - Footings | 11/7/1995 | 11/7/1995 | 11/7/1995 | P | PASS |
|
|
|
11/07/95 338 - basement footings only r- bar placed letter to come from only 2500 psi concrete from the 3500 on the approved plan.
|