INSP - Final | 11/30/1995 | 11/30/1995 | 11/30/1995 | P | PASS |
Jim Sly
|
|
|
FINAL REINSPECT Foundation height and Drainage away from stucture Minimal as per code. Talked to buyer and builder about problem, builder to strip sod from sides and remove soil to get more drainage.
|
INSP - Letter of compliance | 11/30/1995 | 11/30/1995 | 11/30/1995 | | PASS |
Jim Sly
|
|
|
C of C #10339
|
INSP - Letter of compliance | 11/30/1995 | 11/30/1995 | 11/30/1995 | | PASS |
Jim Sly
|
|
|
C of C #10339
|
INSP - Final | 11/27/1995 | 11/28/1995 | 11/28/1995 | A | FAIL |
Jim Sly
|
|
|
Correction notice: Minor energy code items, 6" exposed foundation problems, Major drainage problems Jim Sly
|
INSP - Energy code compliance | 9/15/1995 | 9/15/1995 | 9/15/1995 | P | PASS |
Wes Worcester
|
|
|
09/15/95 342 - exposed celotex in garage attic, called Mike to cover and top chord.
|
INSP - Energy code compliance | 9/15/1995 | 9/15/1995 | 9/15/1995 | P | PASS |
Wes Worcester
|
|
|
09/15/95 342 - exposed celotex in garage attic, called Mike to cover and top chord.
|
INSP - Footings | 7/26/1995 | 7/27/1995 | 7/27/1995 | A | NR |
Wes Worcester
|
|
|
07/26/95 342 - 05. early start. soft soils and placing rebar, maintain m
|