(MICRON BLDG. #25)(ADDITION INTERIOR PHASE) TO CONSTRUCT INTERIOR FINISHES, PARTITIONS, CEILINGS AND ALL OTHER MATERIALS AND SYSTEMS TO COMPLETE APPROXIMATELY 25,300 SQUARE FEET OF NEW AREA. CONSTRUCTION TO BE ALL NON-COMBUSTIBLE MATERIALS AND THE STRUCTURE IS TO BE FULLY FIRE SPRINKLERED. ALL PER APPROVED PLANS ON FILE.RG P.C.#466 INITIAL CERTIFICATE OF VALUE ON FILE. ELECTRICAL 1,674,918 COMBINED PLG/MEC. 11,683,561.00 FIRE SPRINKLER. 26,500
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Letter of compliance  1/9/1997 PASS
ISSUED #12413 C OF C BY MJW AS PER 301.
INSP - Final1/9/19971/7/19971/7/1997 PASS
INSP - Final1/3/19971/3/19971/3/1997PPASS
DetailsJim Storey
01/03/97 301 - FNL -OK FINAL routed for sign offs.
INSP - Final12/19/199612/30/199612/30/1996APASS
Details
12/30/96 405 - also hydro fab2 bldg 3 w/john a 9,###-#### complete c/n for bldg 25 addition c/n items complete......verify letter of intent on incomplete mezz, ladd removed
INSP - Final11/27/199612/4/199612/4/1996ACANC
DetailsJim Storey
INSP - Final11/27/199612/4/199612/4/1996PPASS
DetailsJim Storey
12/04/96 301 - HAD TO MOVE THIS TO PM BECAUSE OF THE MEETING. FRAM-OK FRAMING
INSP - Temporary occupancy11/8/199611/13/199611/13/1996 PASS
Details
TEMP OCC APPROVED, C/N ISSUED ON DOCUMENTATION NEEDED FOR ALARMS & SPRINKLERS
INSP - Ceiling grid11/20/199511/21/199511/21/1995APASS
DetailsJim Storey
11/20/95 301 -