INSP - Final | 1/14/1997 | 1/14/1997 | 1/14/1997 | | PASS |
|
|
|
|
INSP - Occupancy Sign-off | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
|
|
|
Inspected by Art Yingling - Proj. is in compliance w/CU-21-95/DR-15-95. Final Occ. Signed - OK to release Bond (10/10/96 - $79,123.00).
|
INSP - Occupancy Sign-off | 11/15/1996 | 11/15/1996 | 11/21/1996 | | FAIL |
|
|
|
Issues of meeting DR cond. #1b, #1e (add'l shrubs and moving a tree). Providing specific approved shrubs. Cond. #1c - ground cover for NW Pad/pedestrian walkway, stiping drives and issue of Off-Premise Adv. Sign
|
INSP - Final | 10/16/1996 | 10/16/1996 | 10/16/1996 | | PASS |
|
|
|
/ / 405 - final occ check
|
INSP - Final | 10/14/1996 | 10/14/1996 | 10/14/1996 | | PART |
|
|
|
OK for temp. occ. omly. Items on CN dated 10/11/96 still outstanding.
|
INSP - Final | 10/11/1996 | 10/11/1996 | 10/11/1996 | | PASS |
|
|
|
temp occ approved, c/n issued for perm
|
INSP - Temporary occupancy | 10/10/1996 | 10/10/1996 | 10/10/1996 | | PASS |
|
|
|
Insp for temp. by Art Y./Required bonding for landscaping & sprinkler system/Bond posted for $79,123.00 on 10/10/96 temporary occupancy signed.
|
INSP - Conference | 10/3/1996 | 10/3/1996 | 10/3/1996 | | PASS |
|
|
|
/ / 405 - punchlist, lane markers, hvac smokes to create list for temp pending alarm system changes
|
INSP - Conference | 10/1/1996 | 10/1/1996 | 10/1/1996 | A | FAIL |
Wes Worcester
|
|
|
NEED TO FIRECAULK RATED WALLS AND COMPLETE bcec
|
INSP-Conference | 9/27/1996 | 10/1/1996 | 10/1/1996 | A | FAIL |
|
|
|
09/30/96 405 - c/n issued on several items
|
INSP - Conference | 9/30/1996 | 9/30/1996 | 9/30/1996 | A | NH |
Wes Worcester
|
|
|
|
INSP - Conference | 9/30/1996 | 9/30/1996 | 9/30/1996 | P | NR |
Wes Worcester
|
|
|
checked lower handicapped and hot H2O lines not insulated
|
INSP - Conference | 9/27/1996 | 9/27/1996 | 9/27/1996 | P | PART |
Wes Worcester
|
|
|
Handicap insp
|
INSP - Carpentry | 7/25/1996 | 7/25/1996 | 7/25/1996 | P | NH |
Wes Worcester
|
|
|
corridors for fire caulking no one there at 5 pm
|
INSP - Framing/Rough-in | 6/24/1996 | 6/25/1996 | 6/25/1996 | A | PART |
Wes Worcester
|
|
|
06/25/96 342 - 8:15 A.M. TUESDAY c-3 and c-4 fire caulking ok
|
INSP - Framing/Rough-in | 6/21/1996 | 6/24/1996 | 6/24/1996 | A | CANC |
Wes Worcester
|
|
|
06/24/96 342 - sent in am but not received until pm as computers were do am 1st thing Tues
|
INSP - Framing/Rough-in | 6/12/1996 | 6/13/1996 | 6/12/1996 | A | PASS |
Wes Worcester
|
|
|
06/12/96 342 - EARLY A.M. area b..3rd flr caulk & frame....106 being done
|
INSP - Framing/Rough-in | 6/11/1996 | 6/12/1996 | 6/12/1996 | A | NR |
Wes Worcester
|
|
|
06/12/96 342 - FRAME AND FIRE CAULK EARLY P.M.
|
INSP - Wall cover | 6/12/1996 | 6/12/1996 | 6/12/1996 | | NR |
Wes Worcester
|
|
|
/ / 342 - area c-1
|
INSP - Framing/Rough-in | 6/11/1996 | 6/11/1996 | 6/11/1996 | P | CANC |
Wes Worcester
|
|
|
06/11/96 342 - also caulking postponed to Wed am at 8 am ì
|
INSP - Framing/Rough-in | 5/16/1996 | 5/16/1996 | 5/16/1996 | P | NR |
Jim Storey
|
|
|
05/16/96 301 - SENT TO YOU, WES IS SICK
|
INSP - Framing/Rough-in | 5/9/1996 | 5/16/1996 | 5/11/1996 | A | CANC |
Wes Worcester
|
|
|
05/15/96 342 - Kim and Jim Storey went by, Wes sick
|
INSP - Framing/Rough-in | 5/9/1996 | 5/14/1996 | 5/9/1996 | A | NR |
Wes Worcester
|
|
|
05/14/96 342 - still firecaulking and bracing trusses.. Called for corre
|
INSP - Framing/Rough-in | 5/8/1996 | 5/9/1996 | 5/3/1996 | A | PART |
Wes Worcester
|
|
|
05/08/96 342 - THURS AM
|
INSP - Carpentry | 4/29/1996 | 4/30/1996 | 4/25/1996 | A | PART |
Wes Worcester
|
|
|
04/30/96 342 - SET FOR 11:30 ì
|
INSP - Carpentry | 4/29/1996 | 4/29/1996 | 4/23/1996 | P | CANC |
Wes Worcester
|
|
|
04/29/96 342 - CORRIDORS 3C & 3B.
|
INSP - Framing/Rough-in | 4/23/1996 | 4/25/1996 | 4/20/1996 | A | PART |
Wes Worcester
|
|
|
04/25/96 342 - AREA B-1 C-1 GUEST ROOMS WOULD LIKE A 9:00AM INSPECTION. still fire caulking and working on shafts and fireproofing steel I beam
|
INSP - Carpentry | 4/15/1996 | 4/16/1996 | 4/16/1996 | A | FAIL |
Wes Worcester
|
|
|
EXTERIOR SHEATHING not stapled on vertical seam and staples have broken paper membrane
|
INSP - Framing/Rough-in | 4/4/1996 | 4/4/1996 | 4/4/1996 | P | FAIL |
Wes Worcester
|
|
|
PRE-FRAMING. AREA C corridors and elevator shaft have been compromised. Letter of Transmittal sent 04/05/96
|
INSP - Conference | 3/1/1996 | 3/1/1996 | 3/1/1996 | P | PASS |
Wes Worcester
|
|
|
1:30 pm please RC channel and 2 hr area sep wall ok to this point
|
INSP - Conference | 2/23/1996 | 2/23/1996 | 2/23/1996 | P | PART |
Wes Worcester
|
|
|
went over spec requests, engineering and architectural rfi's
|
INSP - Carpentry | 2/22/1996 | 2/22/1996 | 2/22/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Wall cover | 2/22/1996 | 2/22/1996 | 2/22/1996 | P | CANC |
Wes Worcester
|
|
|
JIM -C/M CO. 1 PM PER WES..............
|