INSP - Final | 5/28/1996 | 5/29/1996 | 5/29/1996 | P | PASS |
Jim Sly
|
|
|
05/28/96 316 - C/N removed..C/C # 11197
|
INSP - Letter of compliance | 5/29/1996 | 5/29/1996 | 5/29/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 11197
|
INSP - Letter of compliance | 5/29/1996 | 5/29/1996 | 5/29/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 11197
|
INSP - Final | 5/14/1996 | 5/15/1996 | 5/15/1996 | A | FAIL |
Jim Sly
|
|
|
05/14/96 316 - hazardous glazing, found. insulation. C/N
|
INSP - Carpentry | 3/5/1996 | 3/5/1996 | 3/5/1996 | P | PASS |
Jim Sly
|
|
|
Inspection of truss fix....OK
|
INSP - Energy code compliance | 3/1/1996 | 3/1/1996 | 3/1/1996 | P | PASS |
Jim Sly
|
|
|
OK to cover.....Leave off area for truss fix inspection.
|
INSP - Framing/Rough-in | 2/26/1996 | 2/26/1996 | 2/26/1996 | P | FAIL |
Wes Worcester
|
|
|
c/n on eng, plans not in site etc
|
INSP - Footings | 1/8/1996 | 1/9/1996 | 1/9/1996 | A | PASS |
Jim Sly
|
|
|
Poured footings w/o inspection of soil.... looked at pour, soil next to footings, and setbacks...OK
|
INSP - Foundation | 1/8/1996 | 1/9/1996 | 1/9/1996 | A | PASS |
Jim Sly
|
|
|
OK
|