INSP - Final | 3/13/1996 | 3/14/1996 | 3/14/1996 | A | PASS |
Carl Dependahl
|
|
|
03/13/96 340 -
|
INSP - Letter of compliance | 3/14/1996 | 3/14/1996 | 3/14/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Letter of compliance | 3/14/1996 | 3/14/1996 | 3/14/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Final | 3/13/1996 | 3/13/1996 | 3/13/1996 | P | NR |
Carl Dependahl
|
|
|
03/13/96 340 - FINAL REINSPECT
|
INSP - Conference | 3/12/1996 | 3/12/1996 | 3/12/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Final | 3/11/1996 | 3/11/1996 | 3/11/1996 | P | FAIL |
Carl Dependahl
|
|
|
03/11/96 340 - FINAL REINSPECT
|
INSP - Final | 3/7/1996 | 3/8/1996 | 3/8/1996 | A | NR |
Carl Dependahl
|
|
|
03/07/96 340 - CALLER WANTED MECHANICAL DONE AT THE SAME TIME AS OUR FIN DIDN'T HAVE A MECH. NUMBER AVAILABLE. I GAVE HIME TO RITA BUT I AM LETTING YOU KNOW SO IN CASE IT DOESN'T GET TO YOU IN TIME YOU WILL BE FOREWARNED.........
|
INSP - Energy code compliance | 2/15/1996 | 2/15/1996 | 2/15/1996 | P | PASS |
Carl Dependahl
|
|
|
02/15/96 340 -
|
INSP - Framing/Rough-in | 2/15/1996 | 2/15/1996 | 2/15/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 -
|
INSP - Framing/Rough-in | 2/14/1996 | 2/14/1996 | 2/14/1996 | P | PART |
Carl Dependahl
|
|
|
02/14/96 340 -
|
INSP - Framing/Rough-in | 2/12/1996 | 2/13/1996 | 2/13/1996 | A | FAIL |
Carl Dependahl
|
|
|
02/13/96 340 -
|
INSP - Framing/Rough-in | 2/8/1996 | 2/9/1996 | 2/9/1996 | P | FAIL |
Carl Dependahl
|
|
|
02/09/96 340 -
|
INSP - Stop Work Order | 12/1/1995 | 12/1/1995 | 12/1/1995 | | PASS |
|
|
|
/ / 338 - correction issued
|