INSP - Final | 2/12/1998 | 2/12/1998 | 2/12/1998 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL
|
INSP-Final Inspection | 2/10/1998 | 2/12/1998 | 2/12/1998 | A | PASS |
Rick Jackson
|
|
|
remaining issues from correction notice completed. occupancy approved.
|
Permanent Occupancy | | 2/12/1998 | 2/12/1998 | | DONE |
|
|
|
|
INSP - Final | 11/26/1997 | 12/2/1997 | 12/2/1997 | P | PART |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ada protection under sinks an water lines, special insp. sign off, locking hard ware on three doors at for exit egress
|
INSP-Final Inspection | 11/26/1997 | 12/2/1997 | 12/2/1997 | A | PART |
Rick Jackson
|
|
|
READY AT 9:30 tested sprinkler and alarms - passed. reinstall and verify increase in strobes per approved plans. duct detectors passed. reverify access control entry doors without power.
|
INSP-Sprinkler Rough-in/Hydro | 11/4/1997 | 11/5/1997 | 11/5/1997 | A | PART |
Joe Tawney
|
|
|
11/05/97 406 - around 10:00 if possible OK ON HYDRO TEST EXCEPT FOR FDC PIPING RICK TO RESOLVE
|
INSP - Framing/Rough-in | 10/22/1997 | 10/22/1997 | 10/23/1997 | P | PASS |
Jim Storey
|
|
|
10/22/97 301 - CEILING GRIDS CLG -OK CEILING COVER ì
|
INSP - Framing/Rough-in | 10/14/1997 | 10/14/1997 | 10/14/1997 | P | PART |
Jim Storey
|
|
|
10/14/97 301 - trans to bob.a
|
INSP-Sprinkler Rough-in/Hydro | 9/30/1997 | 9/30/1997 | 9/30/1997 | A | PASS |
Rick Jackson
|
|
|
hydro test of underground - pass
|
INSP - Wall cover | 9/25/1997 | 9/26/1997 | 9/26/1997 | A | PASS |
Jim Storey
|
|
|
09/26/97 301 - CEILING AND GRID INSPECTION ALSCOTT INC. SCLG-OK SUSPENDED CEILING
|
INSP - Wall cover | 9/19/1997 | 9/22/1997 | 9/22/1997 | A | PASS |
Jim Storey
|
|
|
09/22/97 301 - CEILING GRID ok west atria
|
INSP - Framing/Rough-in | 9/15/1997 | 9/16/1997 | 9/16/1997 | A | PASS |
Jim Storey
|
|
|
09/16/97 301 - CEILING GRID 1 st to 2nd grid line ceilling ok for cover. revisions and approved.
|
INSP-Sprinkler Rough-in/Hydro | 9/16/1997 | 9/16/1997 | 9/16/1997 | P | PART |
Rick Jackson
|
|
|
partial inspection of museum area. gave okay to cover high ceiling area only.
|
INSP - Framing/Rough-in | 9/15/1997 | 9/15/1997 | 9/15/1997 | P | NR |
Jim Storey
|
|
|
09/15/97 301 - ceiling grid WIP -WORK IN PROGRESS will call for insp. upon completion of work in are needed for cover
|
INSP-Sprinkler Rough-in/Hydro | 9/4/1997 | 9/8/1997 | 9/8/1997 | A | CANC |
|
|
|
10:30 They called and cancelled, not ready
|
INSP-Supply line flush | 9/4/1997 | 9/5/1997 | 9/5/1997 | A | PASS |
|
|
|
8:30 flushed from piv
|
INSP - Framing/Rough-in | 7/10/1997 | 7/10/1997 | 7/10/1997 | P | PASS |
Jim Storey
|
|
|
07/10/97 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 7/2/1997 | 7/3/1997 | 7/3/1997 | A | NR |
Jim Storey
|
|
|
07/03/97 301 - for the fire something he said that he needed a rough-in they say... when they say it directly to me and not to the ghost in my computer
|
INSP-Sprinkler Rough-in/Hydro | 7/3/1997 | 7/3/1997 | 7/3/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - SPKLR ROUGH IN OK TO COVER AREA ABOVE ATRIUM
|
INSP - Wall cover | 6/30/1997 | 6/30/1997 | 6/30/1997 | A | PART |
Jack Frank
|
|
|
this is a low voltage contractor I posted a cor. under building permit NEC, 348-10, 350-16, 348-12, 370-29, cor. made partial 09 ok jf
|
INSP - Framing/Rough-in | 5/28/1997 | 5/28/1997 | 5/28/1997 | P | PASS |
Jim Storey
|
|
|
05/28/97 301 - FRAM-OK FRAMING 1 AND 2 FLOORS
|
INSP - Conference | 3/7/1997 | 3/7/1997 | 3/7/1997 | P | PART |
Jim Storey
|
|
|
03/07/97 301 - deck ok pending special insp reports.
|
INSP - Conference | 2/27/1997 | 2/27/1997 | 2/27/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - RECIVED FLOOD PLAIN CERTIFICATION
|
INSP - Framing/Rough-in | 1/28/1997 | 1/28/1997 | 1/28/1997 | P | PART |
Jim Storey
|
|
|
01/28/97 301 - FRAM-OK FRAMING SWITCH GEAR ROOM, COM RM.FIRST FLOOR
|
INSP - Flatwork | 1/15/1997 | 1/15/1997 | 1/16/1997 | P | PASS |
Jim Storey
|
|
|
01/16/97 301 - SLAB ok
|
INSP - Carpentry | 12/19/1996 | 12/20/1996 | 12/20/1996 | A | PASS |
Jim Storey
|
|
|
12/20/96 301 - beams for 2nd floor. FRMS-OK FORMS-REBAR special insp on site report pending conf/w s.i. job track.
|
INSP - Carpentry | 12/19/1996 | 12/19/1996 | 12/19/1996 | P | PASS |
|
|
|
12/19/96 333 - GEN -GENERAL INSPECTION
|
INSP - Flatwork | 11/14/1996 | 11/15/1996 | 11/15/1996 | A | PASS |
Wes Worcester
|
|
|
SLAB ON GRADE ?? SPECIAL INSP.ON JOB. CALLING TO LET YOU KNOW .... poured with special inspector on site, #11 bar ck'd ok on 1st lift
|
INSP - Foundation | 10/31/1996 | 10/31/1996 | 10/31/1996 | P | PASS |
|
|
|
10/31/96 333 - COLUMNS FDN -OK FOUNDATION
|
INSP - Footings | 10/24/1996 | 10/24/1996 | 10/24/1996 | P | PART |
Jim Storey
|
|
|
10/24/96 301 - FRMS-OK FORMS-REBAR COVERED W/SI
|
INSP - Footings | 10/18/1996 | 10/21/1996 | 10/21/1996 | A | PART |
Jim Storey
|
|
|
10/21/96 301 - THEY ARE GOING TO POUR AT 1:30 COVERED BY SPECIAL INSP. P
|
INSP - Footings | 10/15/1996 | 10/16/1996 | 10/16/1996 | A | PART |
Jim Storey
|
|
|
10/16/96 301 - POURED WITH SPECIAL INSP. PENDING REPORT.
|
INSP - Carpentry | 10/10/1996 | 10/11/1996 | 10/11/1996 | A | PASS |
Jim Storey
|
|
|
10/10/96 301 - COLUMN PADS FRMS-OK FORMS-REBAR
|
INSP - Flatwork | 10/9/1996 | 10/10/1996 | 10/10/1996 | A | PASS |
Jim Storey
|
|
|
10/09/96 301 - FRMS-OK FORMS-REBAR
|
INSP - Foundation | 10/7/1996 | 10/8/1996 | 10/8/1996 | A | PASS |
Jim Storey
|
|
|
10/08/96 301 - MECHANICAL TUNNEL WALLS FRMS-OK FORMS-REBAR
|
INSP - Footings | 10/3/1996 | 10/4/1996 | 10/4/1996 | A | PART |
Jim Storey
|
|
|
10/04/96 301 - covered by s.i. pending report.
|
INSP - Foundation | 10/2/1996 | 10/3/1996 | 10/3/1996 | A | PASS |
Jim Storey
|
|
|
10/02/96 301 - TUNNEL WALLS??? POURING AT 12:30 FRMS-OK FORMS-REBAR WORK IN PROGESS SPECIAL INSP. IN ROUTE.
|
INSP - Foundation | 9/12/1996 | 9/12/1996 | 9/12/1996 | P | PART |
Jim Storey
|
|
|
09/12/96 301 - covered by s.i.
|
INSP - Footings | 9/10/1996 | 9/11/1996 | 9/11/1996 | P | PASS |
Jim Storey
|
|
|
09/11/96 301 - TUNNELS FRMS-OK FORMS-REBAR WIP -WORK IN PROGRESS w/si
|
INSP - Foundation | 9/5/1996 | 9/6/1996 | 9/6/1996 | A | PART |
Carl Dependahl
|
|
|
09/06/96 340 - WALL ...& COL BASE ENTRY AREA LOOKS OK, PENDING SPEC INSP (JEFF MILLER EISI) ON JOBSITE
|
INSP - Foundation | 9/4/1996 | 9/4/1996 | 9/4/1996 | P | PART |
Jim Storey
|
|
|
09/04/96 301 - covered by si pending report.
|
INSP - Framing/Rough-in | 9/3/1996 | 9/3/1996 | 9/3/1996 | P | CANC |
|
|
|
09/03/96 338 - will be done by 301
|
INSP - Set-back | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PART |
Jim Storey
|
|
|
/ / 301 - footing insp covered by s.i. not a set back isue.
|
INSP - Foundation | 8/29/1996 | 8/29/1996 | 8/29/1996 | P | CANC |
Wes Worcester
|
|
|
FND. REBAR transferred to J Storey
|
INSP - Footings | 8/27/1996 | 8/27/1996 | 8/27/1996 | P | PART |
Jim Storey
|
|
|
08/27/96 301 - covered under special insp. pending report.
|
INSP - Foundation | 8/26/1996 | 8/26/1996 | 8/26/1996 | P | PASS |
Jim Storey
|
|
|
08/26/96 301 - STEMWALL FRMS-OK FORMS-REBAR pending s.i. report.
|
INSP - Footings | 8/22/1996 | 8/22/1996 | 8/22/1996 | P | PASS |
Jim Storey
|
|
|
08/22/96 301 - LATE PM PLEASE FRMS-OK FORMS-REBAR special insp. report pending.
|
INSP - Foundation | 8/20/1996 | 8/20/1996 | 8/20/1996 | P | PASS |
Jim Storey
|
|
|
08/20/96 301 - FRMS-OK FORMS-REBAR special insp on site
|
INSP - Footings | 8/15/1996 | 8/15/1996 | 8/15/1996 | | PART |
Jim Storey
|
|
|
/ / 301 - FRMS-OK FORMS-REBAR 1 st base line covered under special insp.
|
INSP - Foundation | 8/15/1996 | 8/15/1996 | 8/15/1996 | P | CANC |
Jim Sly
|
|
|
08/15/96 316 - Gave to Jim Storey.
|
INSP - Foundation | 8/8/1996 | 8/9/1996 | 8/9/1996 | A | PASS |
Jim Sly
|
|
|
08/09/96 316 - Inspection not sent til PM....poured with special inspect site OK pending special insp report.
|
INSP - Framing/Rough-in | 8/5/1996 | 8/6/1996 | 8/6/1996 | A | PASS |
Jim Sly
|
|
|
08/05/96 316 - STEEL INSP. Footings East straight wall...OK pending sp inspection approval.
|
INSP - Footings | 7/30/1996 | 7/31/1996 | 7/31/1996 | P | PASS |
Jim Sly
|
|
|
07/31/96 316 - Inspection of vetical rebar....east stairwell footing.
|
INSP - Footings | 7/29/1996 | 7/29/1996 | 7/29/1996 | P | PASS |
Jim Sly
|
|
|
07/29/96 316 - Inspection of footing for east stairway...OK pending spec
|