BLD-Final | 7/13/2001 | 7/13/2001 | 7/13/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/13/2001 at 11:18:44. Contact: ###-####.
|
INSP-Conference | 10/12/1998 | 10/12/1998 | 10/12/1998 | A | PART |
Rick Jackson
|
|
|
clarification given as to annual sprinkler test information needed as listed on c/n issued. checked tunnel by cafetorium - still needs sprinkler and strobes
|
INSP-Conference | 5/15/1997 | 5/16/1997 | 5/16/1997 | A | PASS |
|
|
|
17c phased const, standpipes to be in before work restarts above 3rd flr, corridor out of 17b to be sprinkled, bldg to be fully fire sprinkled before any occ, unfinished floors will need freeze protect
|
INSP-Conference | 11/21/1996 | 11/21/1996 | 11/21/1996 | | PASS |
|
|
|
reviewed fd requirements for mothballing shell
|
INSP - Carpentry | 5/24/1996 | 5/24/1996 | 5/24/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gyp nailling exterior, slip j mb atchment.
|
INSP - Conference | 5/3/1996 | 5/3/1996 | 5/3/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - WIP -WORK IN PROGRESS
|