INSP - Final | 11/22/1996 | 11/22/1996 | 11/22/1996 | | PASS |
|
|
|
|
Permanent Occupancy | | 11/22/1996 | 11/22/1996 | | DONE |
|
|
|
|
INSP - Conference | 6/4/1996 | 6/4/1996 | 6/4/1996 | | PASS |
|
|
|
/ / 338 - CHAIR LIFT ACESS OK
|
INSP - Conference | 5/28/1996 | 5/28/1996 | 5/28/1996 | | PART |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ele to be resolved for temp o
|
INSP - Final | 5/10/1996 | 5/13/1996 | 5/13/1996 | A | PART |
Jim Storey
|
|
|
05/10/96 301 - FNL -OK FINAL FOR TOOL HOOKUP OCC. TEMP. PENDING ELE SIGNOFF.
|
INSP - Final | 5/9/1996 | 5/10/1996 | 5/10/1996 | A | PASS |
|
|
|
/ / 338 - to 301
|
INSP - Final | 5/10/1996 | 5/10/1996 | 5/10/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Conference | 5/6/1996 | 5/6/1996 | 5/6/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - DROPPED OFF APROVED RESUBMITLE TO SITE. LEFT ON DUCHS DESK U DUCH.
|
INSP - Conference | 5/3/1996 | 5/3/1996 | 5/3/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - RECIEVED RESUBMITAL AND ROUTED TO PLAN REVIEW AND FIRE DEPT.
|
INSP - Conference | 5/1/1996 | 5/1/1996 | 5/1/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - meeting w/arch/eng./job super/all contractors involved with wall sys. 4/30/96 resubmital requsted to resolve mech correction. 5/1/96 meet d.lightfoot to walk project.
|
INSP - Framing/Rough-in | 4/4/1996 | 4/4/1996 | 4/4/1996 | P | PASS |
|
|
|
1st & 2nd floors. Spec. insp. reports furnished.
|
INSP - Conference | 3/14/1996 | 3/14/1996 | 3/14/1996 | A | PASS |
|
|
|
NEED SPECS ON CLEAN RM. GRID. NEED INSP. REPORTS ON CONCRETE & STEEL.
|
INSP - Framing/Rough-in | 3/13/1996 | 3/14/1996 | 3/14/1996 | A | PASS |
|
|
|
1st floor line C to E.
|