INSP - Final | 4/12/1996 | 4/12/1996 | 4/12/1996 | P | PASS |
|
|
|
letter compliance # 10878
|
INSP - Final | 4/11/1996 | 4/12/1996 | 4/12/1996 | A | CANC |
|
|
|
04/11/96 338 - FINAL REINSPECT 401 scheduled this and will perform same
|
INSP - Letter of compliance | 4/12/1996 | 4/12/1996 | 4/12/1996 | P | PASS |
|
|
|
10878
|
INSP - Letter of compliance | 4/12/1996 | 4/12/1996 | 4/12/1996 | P | PASS |
|
|
|
10878
|
INSP - Footings | 4/11/1996 | 4/11/1996 | 4/11/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - FINAL NOT FOOTING C/N POSTED
|
INSP - Footings | 4/11/1996 | 4/11/1996 | 4/11/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - FINAL NOT FOOTING C/N POSTED
|
INSP - Set-back | 4/11/1996 | 4/11/1996 | 4/11/1996 | P | CANC |
|
|
|
04/11/96 338 - FINAL REINSPECT TO 3O1
|
INSP - Final | 4/10/1996 | 4/10/1996 | 4/10/1996 | P | FAIL |
|
|
|
DECK NOT FINISHED. Rise from finish grade to floor exceeds 8".
|
INSP - Framing/Rough-in | 2/29/1996 | 2/29/1996 | 2/29/1996 | P | PASS |
|
|
|
FRAME REINSPECT
|
INSP - Framing/Rough-in | 2/27/1996 | 2/28/1996 | 2/28/1996 | A | CANC |
|
|
|
02/27/96 338 - 401 AREA GAVE TO HIM
|
INSP - Framing/Rough-in | 3/5/1996 | 2/28/1996 | 2/28/1996 | P | FAIL |
|
|
|
ok to insulate c/n
|
INSP - Framing/Rough-in | 2/26/1996 | 2/26/1996 | 2/26/1996 | P | FAIL |
|
|
|
02/26/96 338 - NO STICKER NO STOP
|
INSP - Conference | 2/20/1996 | 2/20/1996 | 2/20/1996 | | PASS |
|
|
|
/ / 338 - UPDATE WP
|
INSP - Footings | 1/10/1996 | 1/10/1996 | 1/10/1996 | P | PASS |
Jim Storey
|
|
|
01/10/96 301 -
|