Permit Information
Permit NumberBLD96-00070
StatusFinaled
Name FORGE VILLAGE TWNHS
Site Address 4602 N CARLSBAD WAY
Project NameFORGE VILLAGE THS
Customer Number 
ePlanReviewNo
Description
TO BUILD ONE APARTMENT BUILDING OF 5 LIVING UNITS CONSISTING OF TWO UNIT A (970/431/181 SINGLE STORY), TWO UNIT AB (982/431/181 SINGLE STORY), AND ONE UNIT B (1477{940-1ST,537-2ND}/431/181 TWO STORY) SINGLE FAMILY AREAS BUILT TO CONFORM TO "TOWNHOUSE" REQUIREMENTS AS PER APPROVED PLANS. TOTAL SQUARE FOOTAGE IS 5381 LIVING AREA, 2155SF OF GARAGES AND 905SF CONCRETE PATIO. THIS APARTMENT BUILDING WILL NEED TO BE CONVERTED TO TOWNHOUSES UPON RECORDING OF SUBDIVISION IN PROCESS. ACHD # 96-0040. PLAN CHECK #013-96. PRP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final1/7/19991/7/19991/7/1999PPART
DetailsCarl Dependahl
"apartments" permit issued ...to be converted to townhomes; units are now converted. Carl D. from aging
INSP - Final5/1/19985/1/19985/1/1998APASS
DetailsCarl Dependahl
INSP - Final5/28/19975/28/19975/28/1997PNR
DetailsCarl Dependahl
05/28/97 340 - re-inspection five unit apartment before converting to to final 4634 n. carlsbad. way NOBODY HOME
INSP - Final5/27/19975/27/19975/27/1997PFAIL
DetailsCarl Dependahl
05/27/97 340 - fail, nr; wrong address?
INSP - Framing/Rough-in8/21/19968/21/19968/21/1996 PASS
DetailsAlan Hauser
/ / 350 - FRAMING OK TO COVER BLK1 LOT 6
INSP - Framing/Rough-in8/20/19968/20/19968/20/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. ON FRAME AND 5' PROTECTION OUT FROM PARTY WALLS LOT 4, COVER
INSP - Conference8/19/19968/19/19968/19/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. ON PARTY WALL FIRE CAULKING
INSP - Framing/Rough-in8/13/19968/14/19968/14/1996PFAIL
DetailsAlan Hauser
08/14/96 350 - CONF. NOT READY FOR COVER
INSP - Energy code compliance8/13/19968/13/19968/13/1996 PASS
DetailsAlan Hauser
/ / 350 - INSULATION OK ON LOT 2&3 BLK 1K OK TO COVER BUT NOT LOT 4,5,
INSP - Framing/Rough-in8/13/19968/13/19968/13/1996 PASS
DetailsAlan Hauser
/ / 350 - FRAME OK ON LOT 2&3 BLK 1
INSP - Framing/Rough-in8/12/19968/12/19968/12/1996 FAIL
DetailsAlan Hauser
/ / 350 - CORRECTIONS ON BLK1 LOT 2,3 SEAL AT ELECTRICAL PENETRATIONS
INSP - Conference8/7/19968/7/19968/7/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. WITH BUILDER AND SHEETROCKER ABOUT 5'AREA OUT FROM PAR
INSP - Framing/Rough-in8/7/19968/7/19968/7/1996PCANC
DetailsWes Worcester
done by Alan
INSP - Conference7/11/19967/11/19967/11/1996 PASS
DetailsAlan Hauser
/ / 350 - talked with jack and plumbers about plumbing in 1 hr party w going to use metal fittings and fire caulk around penetrations.
INSP - Conference6/27/19966/27/19966/27/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. WITH BUILDER AND BOB ARCHIBALD
INSP - Conference6/27/19966/27/19966/27/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. ON 1 HR. WALL BETWEEN UNITS
INSP - Conference6/27/19966/27/19966/27/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. WITH BUILDER AND BOB ARCHIBALD
INSP - Conference6/27/19966/27/19966/27/1996 PASS
DetailsAlan Hauser
/ / 350 - CONF. WITH BUILDER AND BOB ARCHIBALD
INSP - Carpentry6/18/19966/18/19966/18/1996 FAIL
DetailsJim Sly
/ / 316 - Common wall truss at 5' out...add backing at 16" oc and need engineering for truss carrying extra load.
INSP - Carpentry6/13/19966/13/19966/13/1996PPASS
DetailsJim Sly
06/13/96 316 -
INSP - Carpentry6/4/19966/4/19966/4/1996PPASS
DetailsJim Sly
06/04/96 316 - Inspection of floor befor decking.
INSP - Conference5/31/19966/3/19966/3/1996APASS
DetailsJim Sly
05/31/96 316 - APPOINTMENT BETWEEN 9:30 & 10 A.M. Met with Jack Barber Superintedant and framers...Pat and Tim ..read plan check notes per batum...Questions....answers...etc. (1 1/2 hrs.)
INSP - Foundation5/15/19965/15/19965/15/1996PPASS
DetailsJim Sly
05/15/96 316 - FORGE VILLAGE TOWNHOUSES Footings 4 of 1st 5 units.