INSP - Final | 4/29/1996 | 4/30/1996 | 4/30/1996 | P | PASS |
|
|
|
04/29/96 338 - TUES PM FNL -OK FINAL c/c # 10848
|
INSP - Letter of compliance | 4/30/1996 | 4/30/1996 | 4/30/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED # 10848
|
INSP - Letter of compliance | 4/30/1996 | 4/30/1996 | 4/30/1996 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED # 10848
|
INSP - Wall cover | 3/29/1996 | 3/29/1996 | 3/29/1996 | P | FAIN |
|
|
|
NAILING nailing not conplete will call for the reinspection of same. could not make contact until 4 oclock in the afternoon will have to reinspect 04-01-96
|
INSP - Energy code compliance | 3/26/1996 | 3/26/1996 | 3/26/1996 | | PASS |
|
|
|
/ / 338 - made ok INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 3/25/1996 | 3/26/1996 | 3/26/1996 | A | PASS |
|
|
|
03/26/96 338 - done this am
|
INSP - Framing/Rough-in | 3/22/1996 | 3/25/1996 | 3/25/1996 | A | PASS |
|
|
|
03/25/96 338 - DONE THIS AM
|
INSP - Framing/Rough-in | 3/22/1996 | 3/22/1996 | 3/22/1996 | | FAIL |
|
|
|
/ / 338 - notreadycorrection issued next time reinspection fee will be
|
INSP - Framing/Rough-in | 3/21/1996 | 3/22/1996 | 3/22/1996 | P | CANC |
Carl Dependahl
|
|
|
03/22/96 340 - cancelled by the contractor
|
INSP - Framing/Rough-in | 3/20/1996 | 3/21/1996 | 3/21/1996 | A | FAIL |
|
|
|
03/21/96 338 - READY THURS PM c/n issued do notcover CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 3/21/1996 | 3/21/1996 | 3/21/1996 | | NR |
|
|
|
/ / 338 - not ready
|
INSP - Footings | 3/1/1996 | 3/1/1996 | 3/2/1996 | P | PASS |
|
|
|
03/01/96 338 -
|
INSP - Conference | 2/20/1996 | 2/20/1996 | 2/20/1996 | | PASS |
|
|
|
/ / 338 - UPDATE WP
|