INSP - Final | 12/17/1996 | 12/17/1996 | 12/17/1996 | P | PASS |
Carl Dependahl
|
|
|
12/17/96 340 - REINSPECTION ok
|
INSP - Letter of compliance | 12/17/1996 | 12/17/1996 | 12/17/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - lc issued
|
INSP - Letter of compliance | 12/17/1996 | 12/17/1996 | 12/17/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - lc issued
|
INSP - Final | 12/13/1996 | 12/13/1996 | 12/15/1996 | P | FAIL |
Carl Dependahl
|
|
|
12/13/96 340 - C/N, PLBG FINAL,AIR SEAL, GAR. PENETRATIONS, NO CRAWL ACC
|
INSP - Conference | 11/27/1996 | 11/29/1996 | 11/29/1996 | P | PART |
Wes Worcester
|
|
|
discuss final requirements w/Cael
|
INSP - Energy code compliance | 6/13/1996 | 6/14/1996 | 6/14/1996 | A | PASS |
Carl Dependahl
|
|
|
06/13/96 340 - A.M.C/N OK
|
INSP - Framing/Rough-in | 6/13/1996 | 6/14/1996 | 6/14/1996 | A | PASS |
Carl Dependahl
|
|
|
06/13/96 340 - FRAME REINSPECT. A.M. C/N OK
|
INSP - Energy code compliance | 6/12/1996 | 6/13/1996 | 6/13/1996 | P | NR |
Carl Dependahl
|
|
|
06/13/96 340 - NEED ENG'G, KEEP CN
|
INSP - Framing/Rough-in | 6/10/1996 | 6/10/1996 | 6/10/1996 | P | FAIL |
Carl Dependahl
|
|
|
06/10/96 340 - c/n ok to ins
|
INSP - Carpentry | 5/31/1996 | 5/31/1996 | 5/31/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - CHK SHEATHING, SPOKE W/ OWNER/BLDR, OK TO BEGIN STUCCO INSTA
|
INSP - Carpentry | 5/30/1996 | 5/30/1996 | 5/30/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - need air pckge, sealing, nail off sheathing prior to stucco
|
INSP - Framing/Rough-in | 5/30/1996 | 5/30/1996 | 5/30/1996 | | FAIL |
|
|
|
CN issued, not ready.
|
INSP - Framing/Rough-in | 5/29/1996 | 5/30/1996 | 5/30/1996 | A | |
Bob Archibald
|
|
|
THIS IS READY FOR AM THURSDAY
|
INSP - Carpentry | 5/7/1996 | 5/7/1996 | 5/7/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - HAS > 10' WALLS MAY REQ ENG
|
INSP - Foundation | 3/14/1996 | 3/14/1996 | 3/14/1996 | P | PART |
Carl Dependahl
|
|
|
03/14/96 340 -
|
INSP - Footings | 3/12/1996 | 3/13/1996 | 3/13/1996 | A | PART |
Carl Dependahl
|
|
|
03/13/96 340 -
|