INSP - Conference | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PART |
Wes Worcester
|
|
|
discussed 2 hr area separation walls
|
INSP - Final | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
Wes Worcester
|
|
|
ok after electrical, finishing handrail and carpet while I was there
|
INSP - Final | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Letter of compliance | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
Wes Worcester
|
|
|
will pick up after electrical ISSUED #12334 C OF C BY 342 THIS DATE.
|
INSP - Final | 12/5/1996 | 12/6/1996 | 12/6/1996 | A | FAIL |
Wes Worcester
|
|
|
other insp, hinges, handrail missing, handrail too high, carpet not done, bcec not done, smk detectors incorrect in vault area...
|
INSP - Energy code compliance | 10/2/1996 | 10/2/1996 | 10/2/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 10/2/1996 | 10/2/1996 | 10/2/1996 | P | PASS |
Wes Worcester
|
|
|
BETWEEN 2 AND 2:30 PM.
|
INSP - Energy code compliance | 10/1/1996 | 10/1/1996 | 10/1/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 10/1/1996 | 10/1/1996 | 10/1/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 9/26/1996 | 9/27/1996 | 9/27/1996 | P | PASS |
Wes Worcester
|
|
|
BETWEEN 1:30 & 2 P.M. APPOINTMENT
|
INSP - Framing/Rough-in | 9/23/1996 | 9/23/1996 | 9/23/1996 | P | NR |
Wes Worcester
|
|
|
$42 reinspection fee due
|
INSP - Footings | 7/25/1996 | 7/25/1996 | 7/25/1996 | P | PART |
Wes Worcester
|
|
|
poured w/o insp
|
INSP - Foundation | 7/25/1996 | 7/25/1996 | 7/25/1996 | P | NR |
Wes Worcester
|
|
|
string property lines at frame
|