Permanent Occupancy | | 1/10/1997 | 1/10/1997 | | DONE |
|
|
|
|
INSP - Final | 1/3/1997 | 1/3/1997 | 1/3/1997 | P | FAIL |
Jim Sly
|
|
|
01/03/97 316 - No Occupancy request form at jobsite....Couldn't contact status is... Told Jennie Field to tell contractor of failed inspection.
|
INSP - Final | 8/14/1996 | 8/15/1996 | 8/15/1996 | A | TEMP |
Jim Sly
|
|
|
A.M. Temp.Occ. C/N for ACHD and Plumb final sign off.
|
INSP - Conference | 7/9/1996 | 7/9/1996 | 7/9/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - SENT LETTER OF TRANS TO JOHN COOK, ARCH. RE: SLOPE AT LANDIN FIXED
|
INSP - Energy code compliance | 7/1/1996 | 7/1/1996 | 7/1/1996 | P | PASS |
|
|
|
07/01/96 338 -
|
INSP - Framing/ Rough-in | 7/1/1996 | 7/1/1996 | 7/1/1996 | | PASS |
|
|
|
/ / 338 - corredtions completed
|
INSP - Carpentry | 6/27/1996 | 6/27/1996 | 6/27/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - CHK'D TRUSS DETAIL...BLOCKING STILL NEEDED, KEEP CN
|
INSP - Framing/Rough-in | 6/26/1996 | 6/27/1996 | 6/27/1996 | A | FAIL |
Carl Dependahl
|
|
|
/ / 340 - A.M. C/N OK TO INS
|
INSP - Carpentry | 6/17/1996 | 6/17/1996 | 6/17/1996 | P | PART |
Carl Dependahl
|
|
|
06/17/96 340 - SHEAR WALLS...chk'd walls & roof nailing, verbal to renai and west side bldg...wall#2
|
INSP - Carpentry | 5/31/1996 | 5/31/1996 | 5/31/1996 | P | PART |
Carl Dependahl
|
|
|
05/31/96 340 - HD'S LOOK OK, NOT SURE WHAT THEY WANTED, NOBODY ONSITE
|
INSP - Foundation | 5/22/1996 | 5/22/1996 | 5/22/1996 | P | PART |
Carl Dependahl
|
|
|
05/22/96 340 - REC'D ENG'S LETTER, PART
|
INSP - Foundation | 5/8/1996 | 5/8/1996 | 5/8/1996 | P | PART |
Carl Dependahl
|
|
|
05/08/96 340 - OK TO WET SET BOLTS & PAHD42'S, HAS LOCATIONS MARKED...NE SLAB
|
INSP - Footings | 5/7/1996 | 5/7/1996 | 5/7/1996 | P | PART |
Carl Dependahl
|
|
|
05/07/96 340 - COMM'L BLDG, NO SPEC INSP REQ'D; NEED COMPACTION DATA FOR OK TO POUR FOOTERS
|