INSP - Final | 8/16/1996 | 8/19/1996 | 8/19/1996 | A | PASS |
Alan Hauser
|
|
|
08/19/96 350 - CALL RON ###-#### FOR ACCESS. FINAL OK
|
INSP - Letter of compliance | 8/19/1996 | 8/19/1996 | 8/19/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C#11622
|
INSP - Letter of compliance | 8/19/1996 | 8/19/1996 | 8/19/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C#11622
|
INSP - Energy code compliance | 6/21/1996 | 6/21/1996 | 6/21/1996 | | PASS |
Wes Worcester
|
|
|
06/19/96 342 -
|
INSP - Energy code compliance | 6/18/1996 | 6/19/1996 | 6/19/1996 | P | CANC |
Alan Hauser
|
|
|
06/19/96 350 - DONE BY #342
|
INSP - Energy code compliance | 6/20/1996 | 6/19/1996 | 6/19/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Energy code compliance | 6/20/1996 | 6/19/1996 | 6/19/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 6/12/1996 | 6/13/1996 | 6/13/1996 | P | PASS |
Alan Hauser
|
|
|
06/13/96 350 - THURS. P.M. ok to insulate, some corrections to check on energy compliance
|
INSP - Conference | 6/12/1996 | 6/12/1996 | 6/12/1996 | | FAIL |
Jim Sly
|
|
|
/ / 316 - Met Alan Hauser on site for 1st frame inspection.
|
INSP - Framing/Rough-in | 6/11/1996 | 6/12/1996 | 6/12/1996 | A | FAIL |
Alan Hauser
|
|
|
06/11/96 350 - no inspect. only did partial inspection mech. not done
|
INSP - Footings | 4/1/1996 | 4/1/1996 | 4/1/1996 | P | FAIL |
Jim Sly
|
|
|
04/01/96 316 - poured W/O inspection. Looked at soil a couple of days a too much water in forms...setbacks...?
|
INSP - Footings | 3/27/1996 | 3/28/1996 | 3/28/1996 | A | FAIL |
Jim Sly
|
|
|
03/27/96 316 - No one at site...raining and forms filled with mud and wa
|