INSP - Final | 9/16/1996 | 9/17/1996 | 9/17/1996 | A | PASS |
Jim Storey
|
|
|
09/16/96 301 - CALL TONY AT ###-#### SO HE CAN MEET YOU THERE FNL -OK FINAL
|
Permanent Occupancy | | 9/17/1996 | 9/17/1996 | | DONE |
|
|
|
|
INSP - Final | 9/13/1996 | 9/13/1996 | 9/16/1996 | P | PASS |
Jim Storey
|
|
|
09/13/96 301 - FNL -OK FINAL
|
INSP - Final | 9/3/1996 | 9/3/1996 | 9/3/1996 | | PASS |
|
|
|
/ / 405 - reviewed inventory of haz mat, moving r-12 tanks to aerosol comply at that point. perm occ signed
|
INSP - Final | 8/27/1996 | 8/27/1996 | 8/27/1996 | | PART |
|
|
|
/ / 405 - review inventory levels list of inventory provided w/o quant pending providing inventory qtys
|
INSP - Final | 8/27/1996 | 8/27/1996 | 8/27/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - TCO -TEMP C OF O ISSUED
|
INSP - Final | 8/26/1996 | 8/26/1996 | 8/26/1996 | | FAIL |
|
|
|
/ / 405 - reinspection w/structural still need inventory of flam and comb and aerosols
|
INSP - Final | 8/26/1996 | 8/26/1996 | 8/26/1996 | P | FAIL |
Jim Storey
|
|
|
08/26/96 301 - SCHUCK'S/ AROUND 3:00 IF POSSIBLE CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 8/26/1996 | 8/26/1996 | 8/26/1996 | | FAIL |
|
|
|
/ / 405 - DROPPED OFF nfpa CERT FORM 8/23 several issues not complete from c/n
|
INSP - Final | 8/21/1996 | 8/22/1996 | 8/22/1996 | A | FAIL |
|
|
|
08/22/96 405 - c/n issued...reinspect monday aM
|
INSP - Wall cover | 8/19/1996 | 8/19/1996 | 8/19/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - fire wall ok on conopy
|
INSP - Framing/Rough-in | 8/15/1996 | 8/15/1996 | 8/15/1996 | | FAIL |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED resubmital to show how 1 hr protection to be aplied at store front wall 17 ft prop line.
|
INSP - Carpentry | 7/24/1996 | 7/24/1996 | 7/24/1996 | P | PART |
Wes Worcester
|
|
|
what I ck'd at front edge was ok. Kim supposedly ck'd two edges and middle area but did not sign anything, as per contractor
|
INSP - Conference | 7/24/1996 | 7/24/1996 | 7/24/1996 | P | PART |
Wes Worcester
|
|
|
discussed plan w/steed rep
|
INSP - Roof | 7/24/1996 | 7/24/1996 | 7/24/1996 | | PASS |
|
|
|
/ / 333 - ROOF NAILING OK
|
INSP - Roof | 7/23/1996 | 7/24/1996 | 7/24/1996 | A | NR |
Jim Storey
|
|
|
07/24/96 301 - transphered to wes w.
|
INSP - Masonry | 7/8/1996 | 7/8/1996 | 7/8/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - Inspection of N. 1hr wall...1st lift, grout, rebar, & vemicu
|
INSP - Conference | 6/27/1996 | 6/27/1996 | 6/27/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - Pre-Construction conference.
|
INSP - Footings | 6/27/1996 | 6/27/1996 | 6/27/1996 | | CANC |
Jim Sly
|
|
|
/ / 316 - Cancel...should of been Electrical inspection.
|
INSP - Foundation | 6/27/1996 | 6/27/1996 | 6/27/1996 | P | CANC |
Wes Worcester
|
|
|
GIVEN TO JSLY
|
INSP - Foundation | 6/24/1996 | 6/24/1996 | 6/24/1996 | | PASS |
Jim Sly
|
|
|
06/21/96 316 - FND. REBAR
|
INSP - Footings | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Footings | 6/20/1996 | 6/20/1996 | 6/20/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - conf. n/r discused rebar placment.
|
INSP - Foundation | 6/20/1996 | 6/20/1996 | 6/20/1996 | P | FAIL |
Jim Sly
|
|
|
06/20/96 316 - FND.REBAR Not ready.
|