INSP - Final | 9/12/1997 | 9/15/1997 | 9/15/1997 | A | PASS |
|
|
|
09/15/97 338 - signed the perm col on the occ req card cathy will sign f
|
Permanent Occupancy | | 9/15/1997 | 9/15/1997 | | DONE |
|
|
|
|
INSP - Final | 8/12/1997 | 8/12/1997 | 8/12/1997 | P | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC
|
INSP-Final Inspection | 8/7/1997 | 8/8/1997 | 8/8/1997 | A | FAIL |
Joe Tawney
|
|
|
08/08/97 406 - temp. occupancy He said that you had set up the time for REINSP FOR FINAL FAIL DOOR HDWRE AND ALARM SYSTEM
|
INSP - Final | 8/5/1997 | 8/5/1997 | 8/5/1997 | P | FAIL |
Joe Tawney
|
|
|
/ / 406 - 5 MIN ALARM TEST ON BATTERY FAIL IND CIRCUITS FAILED TO OPER
|
INSP - Final | 7/25/1997 | 7/29/1997 | 7/29/1997 | A | PART |
|
|
|
07/29/97 338 - signed the temp col for the complete project
|
INSP-Sprinkler Rough-in/Hydro | 7/25/1997 | 7/28/1997 | 7/28/1997 | P | PART |
Joe Tawney
|
|
|
07/28/97 406 - OK ON HYDRO TEST FOR COMPLETE SYSTEM
|
INSP-Conference | 5/29/1997 | 5/30/1997 | 5/30/1997 | A | PASS |
Joe Tawney
|
|
|
05/30/97 406 - LOOKED AT PROPOSED LOCATION OF DETECTORS IN EXHAUST DUCTS ONE DET FOR TWO CELLS VERTICALLY.OK AS LONG AS DET ARE ACCESSIBLE AND AR LISTED FOR SERVICE
|
INSP - Conference | 5/22/1997 | 5/27/1997 | 5/27/1997 | A | NR |
|
|
|
05/27/97 338 - no one knew what was going on
|
INSP - Conference | 5/27/1997 | 5/27/1997 | 5/27/1997 | | PASS |
|
|
|
/ / 338 -
|
INSP-Conference | 5/22/1997 | 5/27/1997 | 5/27/1997 | A | PASS |
Joe Tawney
|
|
|
05/27/97 406 - RESOLVED DOUBLE DOORS IN CORRIDORS ISSUE. AUTO FLUSH BOLT AND SMOKE SEALS ADDED. ONE SET OF DOORS NOT REQ EXIT WILL HAVE SIGN REMO
|
INSP - Final | 5/21/1997 | 5/22/1997 | 5/22/1997 | A | PART |
|
|
|
05/22/97 338 - signed the temp col for phase 2 and phase 3
|
INSP - Final | 5/21/1997 | 5/21/1997 | 5/21/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - FINAL INSP FOR TEMP OCC OK FOR TEMP OCC OF AREAS A, B, & KI
|
INSP - Final | 5/20/1997 | 5/20/1997 | 5/20/1997 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL INSP FOR TEMP OCC OF AREAS A & B FAILED ALARM SYSTEM S MTG OF FIRE EXT
|
INSP-Conference | 5/20/1997 | 5/20/1997 | 5/20/1997 | A | PART |
|
|
|
drop off resubmital, still problems with circuits 1 and 3 agreed on plan for temp use of A while making changes
|
INSP - Partial final | 5/16/1997 | 5/19/1997 | 5/20/1997 | P | |
Jim Storey
|
|
|
|
INSP - Partial final | 5/20/1997 | 5/20/1997 | 5/19/1997 | P | FAIL |
|
|
|
05/20/97 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Partial final | 5/14/1997 | 5/16/1997 | 5/16/1997 | P | CANC |
|
|
|
05/16/97 338 - building acancelled by rick with sundance OTH-OTHER AGENCIES NOT APPROVED
|
INSP-Conference | 5/15/1997 | 5/16/1997 | 5/16/1997 | A | PART |
|
|
|
PICK-UP & REVIEW ALARM PLANS w general/ engr/ elec cont
|
INSP-Conference | 5/15/1997 | 5/15/1997 | 5/15/1997 | A | PART |
|
|
|
mtg at site w/ gen, arch, elec on alarm plan rejection ALL UNDERSTAND PROBLEMS, TO RESUBMIT CHANGES
|
INSP-Sprinkler Rough-in/Hydro | 5/13/1997 | 5/13/1997 | 5/13/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST FOR UNDERGROUND FDC PIPING
|
INSP - Final | 5/6/1997 | 5/12/1997 | 5/11/1997 | A | NR |
|
|
|
05/12/97 338 -
|
INSP-Sprinkler Rough-in/Hydro | 5/9/1997 | 5/9/1997 | 5/9/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST FOR AREAS A & B OK ON ROUGH IN FOR A & B FDC NOT INST OR TESTED
|
INSP-Conference | 5/8/1997 | 5/8/1997 | 5/8/1997 | | PASS |
|
|
|
DISCUSSED REQUIREMENTS FOR SUBMITTAL OF ALARM SYSTEM PLANS
|
INSP-Sprinkler Rough-in/Hydro | 4/30/1997 | 5/2/1997 | 5/2/1997 | A | NR |
Joe Tawney
|
|
|
MIKE ###-#### HYDRO TEST NOT READY ALL PIPING NOT COMPLETE
|
INSP-Sprinkler Rough-in/Hydro | 4/30/1997 | 5/1/1997 | 5/1/1997 | P | NR |
Joe Tawney
|
|
|
RON ###-#### NOT READY RESHED FOR 5/2/97
|
INSP - Conference | 4/30/1997 | 4/30/1997 | 4/30/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - w/ RON RE CORFOAM 4HR INSUL; NEED NER OR EQUIV, CONSULT W/ J
|
INSP - Carpentry | 4/28/1997 | 4/29/1997 | 4/29/1997 | A | PART |
Carl Dependahl
|
|
|
04/29/97 340 - FIREPROOFING. SPOKE W/ RON CH2M HILL SUPT, NEED SPECS
|
INSP - Carpentry | 4/28/1997 | 4/28/1997 | 4/28/1997 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - RE FOAM CORE INSUL AT EXIST MASONRY WALL FOR FIRE RATTING; N
|
INSP - Conference | 4/28/1997 | 4/28/1997 | 4/28/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - W/ PAUL JOHNSON PROJ MGR RE ALARM SYSTEM; REFERRED TO TAWNEY
|
INSP - Conference | 4/25/1997 | 4/25/1997 | 4/25/1997 | P | PASS |
|
|
|
04/25/97 338 - on the proposed 4-hour wall upgrade
|
INSP - Conference | 4/10/1997 | 4/11/1997 | 4/10/1997 | A | PASS |
|
|
|
04/11/97 338 - CONF. SAID YOU SET AN APPOINTMENT FOR AROUND 8 A.M. made with paperwork ì
|
INSP - Masonry | 3/25/1997 | 3/26/1997 | 3/25/1997 | A | PASS |
|
|
|
03/26/97 338 - MADE OK WITH SP INSP APPROVAL
|
INSP - Masonry | 3/20/1997 | 3/21/1997 | 3/19/1997 | P | PASS |
|
|
|
03/21/97 338 -
|
INSP - Masonry | 3/19/1997 | 3/20/1997 | 3/19/1997 | A | PASS |
|
|
|
03/20/97 338 - r-bar placed k with sp insp approval
|
INSP - Masonry | 3/18/1997 | 3/18/1997 | 3/17/1997 | P | PASS |
|
|
|
03/18/97 338 - R-BAR PLACED OK WITH SP INSP APPROVAL
|
INSP - Masonry | 3/14/1997 | 3/17/1997 | 3/16/1997 | P | PASS |
|
|
|
03/17/97 338 - made ok with spec insp pass
|
INSP - Masonry | 3/12/1997 | 3/13/1997 | 3/12/1997 | A | PASS |
|
|
|
03/13/97 338 - made ok with sp inspapproval
|
INSP - Masonry | 3/11/1997 | 3/12/1997 | 3/11/1997 | P | PASS |
|
|
|
03/12/97 338 - made ok with sp insp approval
|
INSP - Masonry | 3/11/1997 | 3/11/1997 | 3/11/1997 | P | PASS |
|
|
|
03/12/97 338 - made ok with sp insp approval
|
INSP - Masonry | 3/10/1997 | 3/10/1997 | 3/9/1997 | P | PASS |
|
|
|
03/10/97 338 - ok with special insp blessing
|
INSP - Framing/Rough-in | 3/4/1997 | 3/5/1997 | 3/4/1997 | P | PASS |
|
|
|
03/05/97 338 -
|
INSP - Masonry | 2/27/1997 | 2/28/1997 | 2/28/1997 | A | PASS |
|
|
|
02/28/97 338 - r-bar placed ok with sp insp ok
|
INSP - Framing/ Rough-in | 2/26/1997 | 2/26/1997 | 2/26/1997 | | NR |
|
|
|
/ / 338 - OTH-OTHER AGENCIES NOT APPROVED c/n issued rated wall const a- building
|
INSP - Framing/Rough-in | 2/24/1997 | 2/26/1997 | 2/26/1997 | A | NR |
|
|
|
02/26/97 338 - RESCHEDULE FOR 02-27-97 #1
|
INSP - Masonry | 2/25/1997 | 2/26/1997 | 2/26/1997 | P | PASS |
|
|
|
02/26/97 338 - MADE OK WITH SPEC INSP OK
|
INSP - Masonry | 2/24/1997 | 2/25/1997 | 2/25/1997 | A | PASS |
|
|
|
02/25/97 338 - made ok qith sp insp ok
|
INSP - Masonry | 2/21/1997 | 2/21/1997 | 2/21/1997 | P | PASS |
|
|
|
02/21/97 338 - made ok with spec insp approval
|
INSP - Masonry | 2/19/1997 | 2/19/1997 | 2/19/1997 | P | PASS |
|
|
|
02/19/97 338 - BOND BEAM MADE OK PENDING SPEC INSP WEATHER PRO IN PLACE
|
INSP - Masonry | 2/18/1997 | 2/18/1997 | 2/18/1997 | P | PASS |
|
|
|
02/18/97 338 - MADE O SPEC INSP MADE OK
|
INSP - Masonry | 2/13/1997 | 2/14/1997 | 2/14/1997 | A | PASS |
|
|
|
02/14/97 338 - SPEC INSP MADEOK WEATHER PRO IN PLACE
|
INSP - Masonry | 2/12/1997 | 2/13/1997 | 2/13/1997 | A | PART |
Jim Sly
|
|
|
02/12/97 316 - Inspection of grout pour and bond beam at 4' ...inmate ce OK pending special inspection and approval.
|
INSP - Masonry | 2/12/1997 | 2/13/1997 | 2/13/1997 | P | PASS |
|
|
|
02/13/97 338 - MADE OK SPECIAL INSP MADEOK WEATHER PRO IN PLACE
|
INSP - Masonry | 2/12/1997 | 2/12/1997 | 2/12/1997 | P | PASS |
|
|
|
02/12/97 338 - madeok spec insp. made ok weather protection in place
|
INSP - Masonry | 2/11/1997 | 2/11/1997 | 2/11/1997 | P | PASS |
|
|
|
02/11/97 338 - spec insp made ok weather pro in place
|
INSP - Masonry | 2/10/1997 | 2/10/1997 | 2/10/1997 | P | PASS |
|
|
|
02/10/97 338 - made ok spec insp made ok weTHER PRO IN PLACE
|
INSP - Masonry | 2/7/1997 | 2/7/1997 | 2/6/1997 | P | PASS |
|
|
|
02/07/97 338 - spec insp made ok weather protec. in place
|
INSP - Masonry | 2/6/1997 | 2/6/1997 | 2/6/1997 | P | PASS |
|
|
|
02/06/97 338 - made o spec insp made ok weather pro in place
|
INSP - Masonry | 2/5/1997 | 2/5/1997 | 2/5/1997 | P | PASS |
|
|
|
02/05/97 338 - made ok sp insp made ok w.p. in place
|
INSP - Masonry | 2/3/1997 | 2/3/1997 | 2/3/1997 | P | PASS |
|
|
|
02/03/97 338 - made ok spec insp made ok weather pro in place
|
INSP - Masonry | 1/29/1997 | 1/29/1997 | 1/28/1997 | P | PASS |
|
|
|
01/29/97 338 - made ok spec insp made ok weather pro in place
|
INSP - Masonry | 1/27/1997 | 1/27/1997 | 1/26/1997 | P | PASS |
|
|
|
01/27/97 338 - SPEC INSP MADE OK WEATHER PRO IN PLACE R-BAR IN PLACE
|
INSP - Masonry | 1/23/1997 | 1/24/1997 | 1/24/1997 | A | PASS |
|
|
|
01/24/97 338 - spec insp made ok weather pro in place r-bar placed cylin
|
INSP - Masonry | 1/23/1997 | 1/24/1997 | 1/24/1997 | P | PASS |
|
|
|
01/24/97 338 - made ok sp insp made ok weather pro in place slab made o
|
INSP - Masonry | 1/23/1997 | 1/24/1997 | 1/24/1997 | A | PASS |
|
|
|
01/24/97 338 - made ok sp insp made ok
|
INSP - Masonry | 1/22/1997 | 1/22/1997 | 1/22/1997 | P | PASS |
|
|
|
01/22/97 338 - made ok weather pro in place r-bar placed made ok
|
INSP - Masonry | 1/21/1997 | 1/21/1997 | 1/20/1997 | P | PASS |
|
|
|
01/21/97 338 - MADE OK SPEC INSP MADE OIK WEATHER PRO IN PLACE
|
INSP - Masonry | 1/17/1997 | 1/17/1997 | 1/17/1997 | P | PASS |
|
|
|
01/17/97 338 - r-bar place spec insp made ok weather pro in place
|
INSP - Masonry | 1/14/1997 | 1/14/1997 | 1/14/1997 | P | PASS |
|
|
|
01/14/97 338 - MADE OK
|
INSP - Foundation | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
|
|
|
01/13/97 338 - R-BAR & WP IN PLACE
|
INSP - Foundation | 1/13/1997 | 1/13/1997 | 1/13/1997 | P | PASS |
|
|
|
r-bar in place spec insp made ok weather protec in place
|
INSP - Masonry | 1/10/1997 | 1/10/1997 | 1/10/1997 | P | PASS |
|
|
|
01/10/97 338 - MADE OK WEATHER PRO IN PLACE
|
INSP - Masonry | 1/9/1997 | 1/9/1997 | 1/9/1997 | P | PASS |
|
|
|
01/09/97 338 - made ok spec insp made ok weather pro in place
|
INSP - Masonry | 1/8/1997 | 1/8/1997 | 1/8/1997 | P | PASS |
|
|
|
01/08/97 338 - GROUT AT 3 PM. made ok weather pro in place spec insp ma
|
INSP - Footings | 1/7/1997 | 1/7/1997 | 1/7/1997 | P | PASS |
|
|
|
01/07/97 338 - made ok spec insp made ok
|
INSP - Framing/Rough-in | 12/26/1996 | 12/27/1996 | 12/27/1996 | P | FAIL |
Carl Dependahl
|
|
|
12/27/96 340 - re-bar 338 AREA, NEED TO RAISE BAR TO 1 1/2" ABOVE GRADE; INSP. SLAB AT CELL AREA.
|
INSP - Footings | 12/13/1996 | 12/13/1996 | 12/12/1996 | P | PASS |
|
|
|
12/13/96 338 - made ok special insp made ok
|
INSP - Masonry | 12/12/1996 | 12/12/1996 | 12/12/1996 | P | PASS |
|
|
|
12/12/96 338 - made ook spec insp and weather prot ok
|
INSP - Foundation | 12/11/1996 | 12/11/1996 | 12/11/1996 | P | PASS |
|
|
|
12/11/96 338 - SPEC INSP MADE OK R-BAR PLACED WEATHER PROTECTION IN PLAC
|
INSP - Footings | 12/10/1996 | 12/10/1996 | 12/10/1996 | P | PASS |
|
|
|
12/10/96 338 - r-bar placed weather prot in place spec insp ok
|
INSP - Foundation | 12/10/1996 | 12/10/1996 | 12/10/1996 | P | PASS |
|
|
|
12/10/96 338 - made ok spec insp ok weather prot in place
|
INSP - Foundation | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
|
|
|
12/09/96 338 - made ok r-bar placed weather prot in place
|
INSP - Conference | 12/5/1996 | 12/6/1996 | 12/6/1996 | A | PASS |
|
|
|
12/06/96 338 - 9:30 AM. made ok
|
INSP - Foundation | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | PASS |
|
|
|
12/06/96 338 - special insp madeok r-bar placed
|
INSP - Foundation | 12/5/1996 | 12/5/1996 | 12/5/1996 | P | PASS |
|
|
|
12/05/96 338 - EARLY PM
|
INSP - Footings | 12/3/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
|
|
|
12/04/96 338 - r-bar placed spec insp made ok
|
INSP - Foundation | 12/3/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
|
|
|
12/04/96 338 - FDN -OK FOUNDATION r-bar placed spec insp made ok
|
INSP - Footings | 11/22/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
|
|
|
11/25/96 338 - made ok poured w/o my insp special insp made ok
|
INSP - Foundation | 11/21/1996 | 11/21/1996 | 11/21/1996 | P | PASS |
|
|
|
11/21/96 338 - made ok spec insp ok r-bar placed
|
INSP - Foundation | 11/19/1996 | 11/20/1996 | 11/21/1996 | P | PASS |
|
|
|
11/21/96 338 - EARLY PM made ok special insp r-bar placed
|
INSP - Footings | 11/15/1996 | 11/18/1996 | 11/18/1996 | A | PASS |
|
|
|
11/18/96 338 - made ok special insp made ok
|
INSP - Footings | 11/14/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
|
|
|
11/15/96 338 - EARLY PM
|
INSP - Footings | 11/13/1996 | 11/14/1996 | 11/14/1996 | P | PART |
Jim Sly
|
|
|
11/14/96 316 - Footings OK pending special insp. OK Inspection of South radius.
|
INSP - Footings | 11/12/1996 | 11/13/1996 | 11/13/1996 | P | PASS |
|
|
|
11/13/96 338 - EARLY PM. madeok poured with special insp only d cram
|
INSP - Footings | 11/6/1996 | 11/7/1996 | 1/3/1980 | P | PASS |
|
|
|
11/08/96 338 - E POURED W/O MY INSP STILL NEED SPECDIAL INSP INFO. OK BE NOTIFIED TO ALL POURS AFTER THISS TIME
|