INSP - Final | 3/12/1997 | 3/12/1997 | 3/11/1997 | P | PASS |
|
|
|
03/12/97 333 - 1ILL BE UNLOCKED AT 1:00 FNL -OK FINAL
|
INSP - Letter of compliance | 3/11/1997 | 3/11/1997 | 3/11/1997 | | PASS |
|
|
|
/ / 333 - letter #12259
|
INSP - Letter of compliance | 3/11/1997 | 3/11/1997 | 3/11/1997 | | PASS |
|
|
|
/ / 333 - letter #12259
|
INSP - Final | 2/21/1997 | 2/24/1997 | 2/24/1997 | A | NR |
Alan Hauser
|
|
|
02/24/97 350 - not ready, need elec. and mech. finals, left notice
|
INSP - Conference | 8/14/1996 | 8/15/1996 | 8/15/1996 | P | CANC |
Alan Hauser
|
|
|
08/15/96 350 - TO BE DONE BY #342
|
INSP - Energy code compliance | 8/14/1996 | 8/15/1996 | 8/15/1996 | P | CANC |
Alan Hauser
|
|
|
08/15/96 350 - TO BE DONE BY #342
|
INSP - Framing/Rough-in | 8/14/1996 | 8/15/1996 | 8/15/1996 | P | CANC |
Alan Hauser
|
|
|
08/15/96 350 - TO BE DONE BY #342
|
INSP - Carpentry | 8/8/1996 | 8/8/1996 | 8/8/1996 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - need 1 hr details
|
INSP - Conference | 8/8/1996 | 8/8/1996 | 8/8/1996 | | PART |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Framing/Rough-in | 8/8/1996 | 8/8/1996 | 8/8/1996 | P | NR |
Wes Worcester
|
|
|
08/08/96 342 -
|
INSP - Carpentry | 8/2/1996 | 8/2/1996 | 8/2/1996 | P | FAIL |
Wes Worcester
|
|
|
1 hr construction in lieu of a parapet is wrong
|
INSP - Conference | 8/2/1996 | 8/2/1996 | 8/2/1996 | P | PART |
Wes Worcester
|
|
|
discussed 1/2 of structure as per townhouse criteria
|
INSP - Framing/Rough-in | 8/1/1996 | 8/2/1996 | 8/2/1996 | A | NR |
Wes Worcester
|
|
|
|