INSP - Final | 12/13/1996 | 12/16/1996 | 12/16/1996 | A | PASS |
Jim Sly
|
|
|
12/13/96 316 - C/N Removed....C/C # 12016
|
INSP - Letter of compliance | 12/16/1996 | 12/16/1996 | 12/16/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 12016
|
INSP - Letter of compliance | 12/16/1996 | 12/16/1996 | 12/16/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 12016
|
INSP - Final | 12/12/1996 | 12/13/1996 | 12/13/1996 | P | NR |
Jim Sly
|
|
|
12/13/96 316 - NR.
|
INSP - Conference | 12/12/1996 | 12/12/1996 | 12/12/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Energy code compliance | 8/19/1996 | 8/19/1996 | 8/19/1996 | P | PASS |
Jim Sly
|
|
|
08/19/96 316 -
|
INSP - Framing/Rough-in | 8/19/1996 | 8/19/1996 | 8/19/1996 | P | PASS |
Jim Sly
|
|
|
08/19/96 316 - C/N removed...OK
|
INSP - Energy code compliance | 8/13/1996 | 8/14/1996 | 8/14/1996 | P | FAIL |
Jim Sly
|
|
|
08/14/96 316 - Waiting for framing to pass.
|
INSP - Framing/Rough-in | 8/13/1996 | 8/14/1996 | 8/14/1996 | P | FAIL |
Jim Sly
|
|
|
08/14/96 316 - Fail.. no transfer loads at micros above stairway as requ previously....42.00 re-inspect fee.
|
INSP - Framing/Rough-in | 8/12/1996 | 8/12/1996 | 8/12/1996 | P | FAIL |
Jim Sly
|
|
|
08/12/96 316 - C/N for misc. Insulation not complete. Contractor to ca frame and energy code insp.
|
INSP - Framing/Rough-in | 8/7/1996 | 8/7/1996 | 8/7/1996 | P | PART |
Jim Storey
|
|
|
08/07/96 301 - 1 P.M. WED. SHE HAS TONS & TONS OF ENGINEERING........!! FRAM-OK FRAMING PENDING LETTER FROM DEAN BBIGS AS TO THE LOCATION OF TIE LOCATIONS VS PLAN REQUIRMENTS. TRUSS BRACING NOTED.
|
INSP - Foundation | 5/30/1996 | 5/30/1996 | 5/30/1996 | P | PART |
Carl Dependahl
|
|
|
05/30/96 340 - PART, NO PLAN,FORMS & HD'S NOT COMPLETE, FTG LOOKS OK
|
INSP - Foundation | 5/20/1996 | 5/20/1996 | 5/20/1996 | P | PASS |
Jim Sly
|
|
|
05/20/96 316 - Setbacks, soil, height...OK. (footings).
|