INSP-Conference | 12/26/1996 | 12/26/1996 | 12/26/1997 | A | PART |
|
|
|
hydrant installed, storage shevles modified to two tiers
|
INSP - Final | 1/8/1997 | 1/8/1997 | 1/8/1997 | | PASS |
|
|
|
THIS WAS FINALED THIS DATE AS PER GEORGE SLANE FOR JIM STOREY.
|
Permanent Occupancy | | 1/8/1997 | 1/8/1997 | | DONE |
|
|
|
|
INSP - Final | 12/6/1996 | 12/9/1996 | 12/9/1996 | P | NR |
|
|
|
TOM - ###-#### wanted perm occupancy without resolving high storage issue. Told contractor the city was waiting for a resubmittal describing how storage will be addressed
|
INSP-Conference | 11/13/1996 | 11/13/1996 | 11/13/1996 | | PASS |
|
|
|
faxed new general contractor copy of c/n issued with open items
|
INSP - Final | 10/23/1996 | 10/24/1996 | 10/24/1996 | A | NR |
Jim Storey
|
|
|
10/24/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED DOOR LABLE VERIFACATION FROM SUPPLIER/ FIRE DOOR OVERHEAD VERIFACATION OPERATION TO BE WITNESSED.
|
INSP - Final | 10/24/1996 | 10/24/1996 | 10/24/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - OTH-OTHER AGENCIES NOT APPROVED TCO -TEMP C OF O ISSUED PENDING F.D. AND FIRE DOOR LABLING MARKING UL LE VERIFACATION ON
|
INSP - Final | 10/23/1996 | 10/23/1996 | 10/23/1996 | | PART |
|
|
|
TEMP OCC PENDING HYDRANT INSTALL AND STORAGE ISSUE
|
INSP-Conference | 10/22/1996 | 10/22/1996 | 10/22/1996 | | PART |
|
|
|
advised owner to reduce storage height of tires and provide proof of contract to install hydrant for temp occ. letter from r ross 11/95 relieves requirement to vent tanks outside
|
INSP - Final | 10/21/1996 | 10/21/1996 | 10/21/1996 | P | FAIL |
|
|
|
TERRY WHITE - ###-#### OR TERRY JULLION AT THE SAME NUMBER. 5 of 7 items still not done on c/n, still no fd plans, no storage plans, added tank vented inside building, c/n expanded
|
INSP - Final | 10/16/1996 | 10/16/1996 | 10/16/1996 | | FAIL |
|
|
|
/ / 405 - c/n issued high piled storage issue, missing hydrant
|
INSP - Carpentry | 10/1/1996 | 10/1/1996 | 10/1/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - draft stop ok
|
INSP - Ceiling grid | 9/30/1996 | 10/1/1996 | 10/1/1996 | A | PASS |
Jim Storey
|
|
|
09/30/96 301 - T-BAR SCLG-OK SUSPENDED CEILING
|
INSP - Wall cover | 9/5/1996 | 9/6/1996 | 9/6/1996 | A | FAIL |
Carl Dependahl
|
|
|
09/06/96 340 - PART, 1HR LID 1ST LAYER OK...LEFT C/N RE FIEBLOCKING AND ARCH'S DETAIL RE COMB AIR & FLUE PENETRATIONS OF 1HR LID. 301 AREA
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | P | PART |
Jim Storey
|
|
|
08/30/96 301 - parcial insp roof deck nailling ok
|
INSP - Masonry | 8/14/1996 | 8/14/1996 | 8/14/1996 | P | PASS |
Jim Storey
|
|
|
08/14/96 301 - covered under special insp by choice of owner. bar insp o sp. jayso kelly p.e. ###-####
|
INSP - Footings | 8/8/1996 | 8/8/1996 | 8/8/1996 | P | NR |
Jim Sly
|
|
|
08/08/96 316 - LATE P.M. Not Ready
|
INSP - Footings | 8/6/1996 | 8/7/1996 | 8/7/1996 | A | PASS |
Jim Sly
|
|
|
08/07/96 316 - Footings west wall..OK pending special insp approval All footings complete.
|
INSP - Foundation | 8/6/1996 | 8/7/1996 | 8/7/1996 | P | PASS |
Jim Sly
|
|
|
08/07/96 316 - Foundation west and south walls OK pending spec insp appr All foundation walls complete.
|
INSP - Foundation | 8/5/1996 | 8/6/1996 | 8/6/1996 | A | PART |
Jim Sly
|
|
|
08/05/96 316 - 2 north walls, and 1 east wall (foundation) OK pending s inspector approval.
|
INSP - Footings | 8/5/1996 | 8/5/1996 | 8/5/1996 | P | PASS |
Jim Sly
|
|
|
08/05/96 316 - Footing #'s 1, 2, 3.
|