INSP - Final | 1/21/1997 | 1/21/1997 | 1/21/1997 | | PASS |
|
|
|
OK FOR PERM OCC
|
INSP - Final | 1/21/1997 | 1/21/1997 | 1/21/1997 | | PASS |
|
|
|
Final
|
Permanent Occupancy | | 1/21/1997 | 1/21/1997 | | DONE |
|
|
|
|
INSP - Final | 1/21/1997 | 1/21/1997 | 1/20/1997 | P | PASS |
|
|
|
01/21/97 338 - SIGNED FINAL COL
|
INSP - Final | 1/13/1997 | 1/14/1997 | 1/15/1997 | P | PART |
|
|
|
01/14/97 338 - conf with joe tawney & prp exit is ok to them ok to sign the occ rec card
|
INSP - Conference | 12/23/1996 | 12/23/1996 | 12/23/1996 | | CONF |
|
|
|
ADV MANAGER THAT THERE WAS POSS PROBLEM WITH EXIT SYSTEM ASKED HIM TO HAVE ARCH CONTACT PLAN REVIEW TO DISCUSS SOLUTION
|
INSP - Final | 12/18/1996 | 12/19/1996 | 12/19/1996 | A | PART |
Joe Tawney
|
|
|
12/19/96 406 - OK FOR TEMP OCC NEED PROPER HDWRE ON RESTROOM DOORS & REPAIR ONE EMERG LIGHT RESOLVE WEST EXIT PROBLEM
|
INSP - Final | 12/18/1996 | 12/19/1996 | 12/17/1996 | P | PART |
|
|
|
12/19/96 338 - made ok signed the occ req card in the temp column
|
INSP - Final | 12/18/1996 | 12/19/1996 | 12/17/1996 | P | FAIL |
|
|
|
12/19/96 338 - no occ rec card on site 2nd time
|
INSP - Conference | 12/17/1996 | 12/17/1996 | 12/17/1996 | | PASS |
|
|
|
/ / 338 - callfrom cincinatti at the general offices they said that th occ rec care down to the city if they could get the proper signoffs I wi approve a temp if all others are done
|
INSP - Framing/Rough-in | 12/16/1996 | 12/16/1996 | 12/16/1996 | P | FAIL |
Carl Dependahl
|
|
|
12/16/96 340 - ceiling cover 338 AREA; C/N NEED ELEC & OTHER OK'S
|
INSP - Ceiling grid | 12/4/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
|
|
|
12/04/96 338 - made ok
|
INSP - Final | 12/4/1996 | 12/4/1996 | 12/4/1996 | P | FAIL |
Joe Tawney
|
|
|
DAN ###-#### SPKLR ROUGH IN FAIL ADDITIONAL HEADS NEEDED
|
INSP - Framing/Rough-in | 10/31/1996 | 11/1/1996 | 11/1/1996 | A | PASS |
|
|
|
11/01/96 338 - MADE OK TO COVER BEHIND THE ELEC SIGNOFFS
|
INSP - Framing/Rough-in | 10/17/1996 | 10/17/1996 | 10/17/1996 | P | PASS |
|
|
|
10/17/96 338 - made ok plans have been located ok to cover framing as th the walls
|
INSP - Framing/Rough-in | 10/16/1996 | 10/16/1996 | 10/17/1996 | A | PASS |
|
|
|
10/17/96 338 - made ok to cover behind the ele insp signoffs
|
INSP - Framing/Rough-in | 10/14/1996 | 10/15/1996 | 10/15/1996 | A | NR |
|
|
|
10/15/96 338 - no approved plans or responsible person on the site
|
INSP - Final | 1/13/1997 | 1/14/1997 | 1/14/1996 | A | FAIL |
Joe Tawney
|
|
|
FINAL FOR PERM OCC FAILED SECOND EXIT ISSUE STILL NOT RESOLVED
|