INSP - Final | 1/15/1997 | 1/16/1997 | 1/16/1997 | P | PASS |
Carl Dependahl
|
|
|
01/16/97 340 - FINAL REINSPECT...BOND POSTED W/ CODE ENF. OK
|
INSP - Letter of compliance | 1/16/1997 | 1/16/1997 | 1/16/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - LC 12178
|
INSP - Letter of compliance | 1/16/1997 | 1/16/1997 | 1/16/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - LC 12178
|
INSP - Final | 1/14/1997 | 1/15/1997 | 1/15/1997 | P | FAIL |
Carl Dependahl
|
|
|
01/15/97 340 - KEEP C/N, NOTIFIED SUPER THAT SMOKE DET'S MUST BE CHANGED
|
INSP - Final | 1/14/1997 | 1/14/1997 | 1/15/1997 | P | FAIL |
Carl Dependahl
|
|
|
01/14/97 340 - C/N, NEED CHK SMOKE DET REQ'S, OTHER AGENCY OK'S, AIR SEA
|
INSP - Wall cover | 9/24/1996 | 9/24/1996 | 9/24/1996 | P | PASS |
Carl Dependahl
|
|
|
09/24/96 340 - SHEAR NAILING OK
|
INSP - Energy code compliance | 9/19/1996 | 9/19/1996 | 9/19/1996 | P | PART |
Carl Dependahl
|
|
|
09/19/96 340 - PART, TOLD TO REMOVE VAPOR BARRIER AT LID (POLY); OK TO C
|
INSP - Framing/Rough-in | 9/19/1996 | 9/19/1996 | 9/19/1996 | | PART |
Carl Dependahl
|
|
|
/ / 340 - REINSP
|
INSP - Framing/Rough-in | 9/16/1996 | 9/16/1996 | 9/16/1996 | P | FAIL |
Carl Dependahl
|
|
|
09/16/96 340 - C/N OK TO INS
|
INSP - Framing/Rough-in | 9/12/1996 | 9/12/1996 | 9/12/1996 | P | FAIL |
Carl Dependahl
|
|
|
09/12/96 340 - cn, n/r
|
INSP - Carpentry | 9/3/1996 | 9/3/1996 | 9/3/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - NEED ENG'G FOR TRUSSES CUT & FIREBLOCKING
|
INSP - Conference | 7/1/1996 | 7/2/1996 | 7/2/1996 | A | PASS |
|
|
|
07/02/96 333 - TUES.A.M. APPOINTMENT 10 A.M. discussed firewlls and energy code
|
INSP - Foundation | 6/27/1996 | 6/28/1996 | 6/28/1996 | A | PASS |
Carl Dependahl
|
|
|
06/28/96 340 - STEEL OK...NEED COMPACTION TESTS FOR SLABS
|
INSP - Footings | 6/26/1996 | 6/27/1996 | 6/27/1996 | P | PASS |
Carl Dependahl
|
|
|
06/27/96 340 - P.M. OK
|
INSP - Footings | 6/25/1996 | 6/26/1996 | 6/26/1996 | P | PART |
Carl Dependahl
|
|
|
06/26/96 340 - THIS HAS BEEN CANCELLED FOR THIS PM - WILL DO THURSDAY. need soils & compaction for slabs...rec'd new fnd detail...ok
|